TCK Project Planning and
Development Guide
Version 1.2
August, 2003
Please
Recycle
Copyright © 2003 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, California 95054, U.S.A. All rights reserved.
Sun Microsystems, Inc. has intellectual property rights relating to technology embodied in this product.Inparticular, and without
limitation, these intellectual property rights may include one or more of the U.S. patents listed at http://www.sun.com/patents and
one or more additional patents or pending patent applications in the U.S. and other countries.
This productisdistributed under licenses restricting its use, copying distribution, and decompilation. No part of this productmay be
reproduced in any form by any means without prior written authorization of Sun and its licensors, if any.
Third-party software, including font technology, is copyrighted andlicensed from Sun suppliers.
Sun, Sun Microsystems, the Sun logo, J2ME, Java, JavaTest, JavaDoc, and the Java Coffee Cup logo trademarks or registered
trademarks of Sun Microsystems, Inc. in the U.S. and other countries.
Federal Acquisitions: Commercial Software - Government Users Subject to Standard License Terms andConditions.
DOCUMENTATION IS PROVIDED “AS IS” AND ALL EXPRESS OR IMPLIED CONDITIONS, REPRESENTATIONS AND
WARRANTIES, INCLUDING ANY IMPLIED WARRANTY OF MERCHANTABILITY, FITNESS FOR A PARTICULARPURPOSE
OR NON-INFRINGEMENT, ARE DISCLAIMED, EXCEPT TO THE EXTENT THAT SUCH DISCLAIMERS ARE HELD TO BE
LEGALLY INVALID.
Copyright © 2003 Sun Microsystems, Inc., 4150 Network Circle, Santa Clara, California 95054, Etats-Unis. Tous droits réservés.
Sun Microsystems, Inc. a les droits de propriété intellectuels relatants à la technologie incorporée dans ce produit. En particulier, et
sans la limitation, ces droits de propriété intellectuels peuvent inclure un ou plus des brevets américains énumérés à http://
www.sun.com/patents et un ou les brevets plus supplémentaires ou les applications de brevet en attentedans les Etats - Unis et les
autres pays.
Ce produit ou document est protégé par un copyright et distribué avec des licences qui en restreignentl'utilisation, la copie, la
distribution, et la décompilation. Aucune partie de ce produit ou document ne peut être reproduitesous aucune forme, par quelque
moyen que ce soit, sans l'autorisation préalable et écrite de Sun et de ses bailleurs de licence, s'il y ena.
Le logiciel détenu par des tiers, et qui comprend la technologie relative aux polices de caractères, est protégé par un copyright et
licencié par des fournisseurs de Sun.
Sun, Sun Microsystems, le logo Sun, J2ME, Java, JavaTest, JavaDoc, et le logo Java Coffee Cup sont des marques de fabriqueou des
marques déposées de Sun Microsystems, Inc. aux Etats-Unis et dans d'autres pays.
CETTE PUBLICATION EST FOURNIE "EN L’ETAT" ET AUCUNE GARANTIE, EXPRESSE OU IMPLICITE, N’EST ACCORDEE, Y
COMPRIS DES GARANTIES CONCERNANT LA VALEUR MARCHANDE, L’APTITUDE DE LA PUBLICATION A REPONDRE
A UNE UTILISATION PARTICULIERE, OU LE FAIT QU’ELLE NE SOIT PAS CONTREFAISANTE DE PRODUIT DE TIERS. CE
DENI DE GARANTIE NE S’APPLIQUERAIT PAS, DANS LA MESURE OU IL SERAIT TENU JURIDIQUEMENT NUL ET NON
AVENU.
ii
Contents
Preface vi
1. Developing a TCK—Introduction 1
Note –Scope of the Task 1
n TCKs and Conformance Testing 2
n Key Decision Points 3
Note –The Java Community Process (JCP) 4
Note –Java Technology—Components 4
FIGURE 1Conformance Testing vs. Product Testing 5
n TCK Development—Timeline 8
Note –Sun’s Java Compatibility Test Tools 9
2. Components of a TCK 13
n TCK Planning Documents 13
n Conformance Rules 14
n Tests and the Test Suite 15
n Test Development Requirements 15
n Test Code Conventions 16
n Appeals Process 17
n Exclude List 17
Note –Test Framework 18
Note – Test Harness 19
n Sun’s JavaTest Harness 20
iii TCK Project Planning and Development Guide August, 2003
n Test Agent 20
n Test Framework Configuration 21
n TCK Documentation 22
n TCK User’s Guide 22
n Test Documentation 22
n Release Notes 22
n Audit Process (Optional) 23
3. Using Java CTT to Build a TCK 25
Note –Creating a TCK—Overview 25
Note –Preparation Phase 26
7.Building the TCK Phase 28
10.Completion Phase 30
6.Maintenance Phase 32
4. Planning a TCK 33
n Initial Questions 33
n Initial Decision Points 36
n TCK Plans 37
n Team Personnel 38
n Resource Estimates 39
n 4.5.1 Time Estimate Assumptions 39
n Time Estimates—Test Development 40
n Time Estimates—Other TCK Elements 41
A. TCK Appeals Process 43
n Introduction 43
2. Appeals Process Guidelines 44
n Test Appeal and Response Forms 45
B. TCK Project Planning Questions 47
n TCK Project Plan 47
n Preparation Plan 48
n TCK Design Document 48
Contents iv
n Test Specifications 49
n Documentation Plan 50
n QA Plan 51
C. Measuring TCK Test Coverage 53
n Overview 53
n Terminology 53
n Assertion Attributes 54
TABLE 2Assertion Coverage 55
TABLE 2Process 55
4. External Specifications 56
4. Assertion Coverage Metrics 57
Note – Specification Testability 57
n Assertion Coverage (Breadth) 58
n Assertion Coverage (Depth) 58
n API Coverage 59
n Process 59
n API Coverage Metric 59
n Signature Coverage 60
Java TCK and CTT Glossary 61
Index 69
v TCK Project Planning and Development Guide August, 2003
vi
Preface
TCK Project Planning and Development Guide explains what you need to do to
develop a Technology Compatibility Kit (TCK) under the Java Community
Process
SM
program. It provides a starting point for a Specification Lead (Spec Lead)
and Expert Group and provides an overview of the process involved in creating a
TCK. It is intended to address the following questions:
What is conformance testing?
What is a TCK?
Why is a TCK important?
What components are required for a TCK?
How do you create a TCK?
What resources are required to create a TCK?
How long does it take to develop a TCK?
How do you plan a TCK development project?
This guide is written for:
Technology Specification Leads (Spec Lead) who scope, plan, and manage the
development of a Java™ Specification Request (JSR) including the TCK that is
used to test implementations of the that specification.
TCK Architects who design a TCK and its component test suites. Architects are
responsible for designing the test suite’s overall architecture, the execution and
application models, and the functional tests required. The architect is also
responsible for designing or configuring a test harness that implements the test
execution model.
Project managers who plan and oversee the actual work of TCK development.
TCK developers who create the TCK tests, test suites, and test framework.
How This Book Is Organized
Chapter 1, “Developing a TCK—Introduction,” provides an overview of Java
Technology Compatibility Kit (TCK) development.
vii TCK Project Planning and Development Guide August, 2003
Chapter 2, “Components of a TCK,” describes the components of a TCK as defined
by the JCP process.
Chapter 3, “Using Java CTT to Build a TCK,” describes how Sun’s Java
Compatibility Test Tools (Java CTT) can be used to help develop a TCK.
Chapter 4, “Planning a TCK,” describes the TCK planning process.
Appendix A, “TCK Appeals Process,” describes the TCK appeals process.
Appendix B, “TCK Project Planning Questions,” describes the questions that
various TCK planning documents need to address.
Appendix C, “Measuring TCK Test Coverage,” describes metrics that can be used
for measuring TCK Test coverage.
“Java TCK and CTT Glossary,” provides a list of Java CTT-related terms and their
definitions.
Related Documents
The following related documents are referred to in this guide and can be found at:
http://jcp.org/en/resources/tdk.
Java Technology Test Suite Development Guide: Describes the theory of how to
design and write the tests that go into any TCK regardless of which test harness
is used. It also provides “how-to” instructions describing how to build your
TCK and write the tests that go into your TCK’s test suite. It includes examples
of testable assertions and the applicable test code.
JavaTest™ Architect’s Guide: Describes the JavaTest™ harness and how to
integrate your tests and the JavaTest harness into your TCK.
TCK Tools & Info: Describes a Technology Compatibility Kit (TCK) and the Java
Compatibility Test Tools (Java CTT) that can be used to help develop a TCK. You
can download the Java CTT tools and documentation from this web site.
JCP: Process Document (found at http://jcp.org): Describes the formal Java
Community Process procedures for developing a new Java technology
specification or revising an existing specification.
JavaTest Users Guide: Describes how to use the JavaTest harness. (Note that if
your TCK uses the JavaTest harness you should include this guide as one of
your TCK deliverables.)
Spec Trac Tool Users Guide: Describes how to install and use the Spec Trac Tool.
Java API Coverage Tool Users Guide. Describes how to install and use the Java
API Coverage Tool.
Signature Test Tool Users Guide: Describes how to install and use the Signature
Test Tool.
Preface viii
TCK Project Plan Template: Provides a template in RTF and HTML formats for
creating a TCK project plan based on IEEE standards and this TCK Project
Planning and Development Guide.
Java Technology Compatibility Kit Users Guide Template: Provides an outline
and template that can be used as the basis of creating a user’s guide for a TCK.
The template can be edited to provide the basis of the user manual that tells
your customers how to use the TCK you are developing. The template is
available in Adobe FrameMaker, Adobe Acrobat, and ASCII plain-text formats.
Accessing Sun Documentation Online
You can find Sun online documentation at the following web sites:
The Java web site provides general information about the Java 2 platform and
related technologies:
http://java.sun.com.
The Java Developer Connection
sm
web site enables you to access Java™
platform technical documentation on the Web:
http://developer.java.sun.com/developer/infodocs.
The Java Community Process (JCP) web site provides information about Java
Technology Specifications, JSRs, and the process of developing them:
http://jcp.org.
The Sun Product Documentation web site provides online versions of Sun
manuals and guides: http://docs.sun.com.
Sun Welcomes Your Comments
We are interested in improving our documentation and welcome your comments
and suggestions. You can email your comments to us at: [email protected].
ix TCK Project Planning and Development Guide August, 2003
1
CHAPTER
1
Developing a TCK—Introduction
This chapter provides an overview of Java Technology Compatibility Kit (TCK)
development and contains the following sections:
Scope of the Task
TCKs and Conformance Testing
Key Decision Points
The Java Community Process (JCP)
Java Technology—Components
Conformance Testing vs. Product Testing
TCK Development—Timeline
Sun’s Java Compatibility Test Tools
Note Up to date information on TCK development, Java Community Process
(JCP) procedures, and the Java™ Compatibility Test Tools (Java CTT) tools are
provided on the JCP web site (http://jcp.org). Should there be differences
between the information provided in this manual and information on the JCP web
site, the web site should be taken as definitive.
Scope of the Task
Designing, creating, and testing a TCK is a large task.
To build a TCK you have to:
Thoroughly understand the technology specification.
Derive testable assertions from the specification.
Determine the tests implied by each assertion, and then prioritize them in order
of importance for testing.
Design, develop, and test the tests for each assertion.
Create a test framework to run, evaluate, and report on tests.
2 TCK Project Planning and Development Guide August, 2003
Assemble the tests, test framework, and documentation into a product suitable
for delivery to customers.
In general terms, the task of developing a TCK is as big as developing and testing
the specification’s Reference Implementation (RI).
Because your TCK is a product that you deliver to your customers, it requires
more development work and support than a simple software test suite for
internal use.
TCKs and Conformance Testing
Java technologies are “cross-platform,” meaning that they run on different hardware
platforms and operating systems. Conformance testing is the process of testing a
technology implementation to make sure that it operates consistently with all other
implementations of the same Java technology specification.
A TCK is a suite of tests, tools, test framework, and documentation that allows an
implementor of an associated Java technology specification to determine if the
implementation complies with the specification. This requires that all tests in the
TCK are implementation-independent, and based only on the written specifications
for a particular Java technology.
For a given platform to be considered conformant (that is, that it complies with
the specification), all of the required TCK tests must pass and meet the testing
requirements. Required tests are those tests listed in the TCK documentation as the
tests that must be passed. (The RI must also pass all required tests and meet the
testing requirements.)
Conformance test development for each feature relies on the existence of a
complete specification and RI for that feature. A TCK performs the tests that ensure
that all implementations of a specification can meet the complete criteria defined by
the specification.
To accomplish its purpose, the TCK test must adequately cover the entire
specification. When this testing is carried out through a formal process, application
developers can be confident that an application will run in a consistent manner
across all tested implementations of the same Java technology specification.
Without the assurance of knowing that the TCK provides adequate coverage,
software developers cannot completely rely upon the published specification
because there is no means to trust that any particular vendor’s implementation has
been correctly constructed.
Conformance testing is important to different groups involved with Java
technologies for different reasons:
Conformance testing ensures that the Java technology does not become
fragmented as it is ported to different operating systems and hardware
environments or re-implemented by different vendors on the same environment.
Chapter 1 Developing a TCK—Introduction 3
Conformance testing benefits Java technology implementors by ensuring a level
playing field for all implementations of that technology.
Conformance testing benefits application developers using the Java
programming language, allowing them to write applications once and then to
deploy them across heterogeneous computing environments without
modification.
Conformance testing benefits application developers who wish to incorporate
features of a Java technology into their applications by allowing them to write to
the Java technology specification rather than to a particular vendor’s
implementation.
Conformance testing allows application users to obtain applications from
disparate sources and deploy them in any user environment with confidence.
For these reasons, developing a TCK that provides adequate test coverage is a
critical task for a JCP Expert Group to undertake when completing a new Java
technology specification.
Deciding what level of test coverage, how the test suite will be automated, and the
conformance requirements (rules) necessary for passing the test suite are all critical
decisions that should be made early in the TCK development process.
When creating a new TCK the Expert Group is not limited in the choice of tools,
test suite format, or management of the changes due to appeals. The Expert Group
should make choices that best meet the requirements and goals of the technology.
See the Java Technology Test Suite Development Guide and JavaTest Architect’s Guide for
detailed information on how to develop TCK tests and test frameworks.
See Chapter 2, “Components of a TCK,” for a detailed description of the elements
that make up a TCK.
Key Decision Points
When first considering TCK development, there are two key decision points that
will have an impact on the amount of resources required, the schedule, and the
overall quality of the finished TCK:
1. What is the average amount of desired test coverage? (See “Initial Decision
Points” on page 36 and Appendix C, “Measuring TCK Test Coverage,” for more
information.)
2. How will the test framework be designed, and particularly which test harness
will be used to run the tests? Sun provides the JavaTest harness, which is
designed for, and used, by many TCKs, but you can use whatever test harness
best suits your needs.
4 TCK Project Planning and Development Guide August, 2003
Note You can also use the other optional Java Compatibility Tools (Java CTT)
that Sun provides. These tools are designed to ease and speed the TCK
development process. They are described in “Sun’s Java Compatibility Test Tools”
on page 9.”
See Chapter 3, “Using Java CTT to Build a TCK,” for a step-by-step description of
the TCK creation process.
See Chapter 4, “Planning a TCK,” for detailed information on planning a TCK
development project and estimating the time and resources required.
The Java Community Process (JCP)
The Java Community Process (JCP) is responsible for the development of Java
technology. As an open, inclusive, membership organization it guides the
development and approval of Java technical specifications, TCKs, and RIs.
In order to ensure both fairness and stability across the Java technology, the JCP has
established a formal procedure for developing new technology specifications and
revising old ones. This process is known as the “JCP process.” The details of the
JCP process are described in full on the JCP web site at: http://jcp.org.
Because your specification has to be developed using the JCP procedures, you may
find it advantageous to assign someone the role of being your “JCP program
manager.” This person to be responsible for ensuring that your specification, TCK,
and RI development meets the JCP requirements in a timely manner.
Java Technology—Components
Under the JCP process, release of a new (or revised) technology specification must
contain three primary components:
1. Specification. A written specification of technology. There are different kinds of
specifications, for example:
Platform editions
Profiles
Optional packages
2. Reference Implementation (RI). The prototype or proof of concept
implementation of the specification. The RI is required to pass the TCK.
Chapter 1 Developing a TCK—Introduction 5
3. Technology Compatibility Kit (TCK). A test kit that Java technology
implementors can use to ensure that their work is conformant with the
technology specification. The TCK must test all aspects of a specification that
impact how conformant an implementation of that specification would be, such
as the public API and all elements of the specification. A vendor's
implementation of a specification is only considered conformant if the
implementation passes the TCK.
As illustrated in FIGURE 1, the development of these three components is best
done together in an interactive manner (as opposed to sequentially).
FIGURE 1 Interactive versus Sequential Development
An interactive approach is more efficient because as the RI is developed to
implement the specification, what is learned may suggest changes that have to be
made to the specification. Similarly, as the TCK is developed and tested against the
RI, problems in the RI or in the specification can be revealed. The interactive
(triangle) process uncovers loopholes and problems earlier in the process of
developing a new specification which in turn results in a more complete and useful
specification. Therefore, the most efficient process is to develop and test all three
components together rather than sequentially one after the other. Note, however, that
you should have a stable draft of the specification before you begin developing the
TCK and RI.
Conformance Testing vs. Product
Testing
Traditional product testing is primarily concerned with:
Product quality
Product robustness
Product performance
Product functionality
Product ease-of-use
Specification
TCK
RI
Specification
RI
TCK
Interactive
Sequential
(Most efficient method)
(Less efficient method)
6 TCK Project Planning and Development Guide August, 2003
But those traditional product testing issues are not the concern or focus of
conformance testing. The concern of conformance testing is to ensure that an
implementation conforms to the specification—regardless of how well it performs.
Therefore, while there are many similarities and overlaps, conformance testing
differs from traditional product testing in the following ways:
Specification conformance. The purpose of Java conformance testing is to
determine whether an implementation of a technology is compliant with the
specification, or multiple specifications, of that technology or technologies. It
does not test for performance or ease-of-use.
Consistency. Conformance testing is a means of ensuring correctness,
completeness, and consistency across all implementations of a technology
specification. In other words, a primary goal of conformance testing is to
provide the assurance that an application will run in a consistent manner across
all tested implementations of a technology.
Scope. The scope of conformance testing is normally to test those features and
areas of an implementation that are likely to differ across implementations. For
example, additional effort may be required to test features that:
Rely on hardware or operating system-specific behavior.
Are difficult to port.
Mask or abstract hardware or operating system behavior.
Assertion based. Each TCK test is based on a specific assertion present in a
technology specification. The test proves the validity of the implementation
being tested.
Similarly, there are significant differences between a TCK that you develop as part
of a Java technology specification and a testing system that a software developer
creates to test the Reference Implementation (RI) of a Java technology specification
(or, for that matter, an end-user application) before releasing it.
For example, some of the differences between a TCK and an internal RI QA test
system include:
Product. A TCK is an actual product delivered to customers. An application test-
suite, on the other hand, is an internal tool used by a developer to test the
developer’s products and is never released to the outside world. When QA
engineers encounter problems with an internal software test system they can go
down the hall and ask for help from the programmer who wrote it, but a TCK is
used by others outside of your company to test their implementations. This
difference has significant implications:
Because it is released to the external world, a TCK has to be put through its
own cycle of Quality Assurance testing the same as any other product.
A TCK must be written and designed for outside end-users. So a TCK has to
have a viable user-interface and comprehensible messages. Error-messages
have to be understandable and useful.
A TCK has to have a good user manual.
You need to provide support services as you would with other kinds of
products delivered to customers.
Chapter 1 Developing a TCK—Introduction 7
Open ended. A TCK has to be designed to test an open-ended set of
implementations.
Black box. A TCK performs “black box” testing that does not require knowledge
of the internal workings of the software being tested.
Configurable. A TCK has to be configurable for all possible test scenarios.
Fairness. A TCK is intended to provide a fair and equal playing field for all
companies developing products under the specification. That is, they all use the
same testing materials (the TCK). This requires that you:
Provide adequate technical support for the TCK.
Provide an appeals process for timely responses to test challenges by users of
the TCK.
Auditable. A TCK has to produce auditable results.
Since TCKs measure a Java technology implementation's conformance to a
specification, it is normally inappropriate to test unspecified product qualities such
as:
Runtime performance
Stress/loading capabilities
Robustness/stability over time
Other product qualities that are not defined by the specification
These product tests are important to the commercial viability of an implementation
and should be tested as part of product quality assurance (QA) testing, however,
they are not relevant to conformance testing.
8 TCK Project Planning and Development Guide August, 2003
TCK Development—Timeline
There are four basic stages in the JCP process. TABLE 1 summarizes how TCK
development fits into these JCP stages.
The detailed, specific technology development requirements and procedures are
described in the JCP: Process Document on the JCP web site at: http://jcp.org.
Note The JCP web site, and particularly the JCP: Process Document provides the
official, up to date, statement of JCP procedures and requirements. Should there be
differences between the information provided in this manual and information on
the JCP web site, the web site should be taken as definitive.
TABLE 1 Recommended TCK Development Phases and JCP Process Steps
TCK Development Phases JCP Process
JSR Initiation Stage
“Preparation Phase” on page 26
Review materials
Mark up specification first draft
Create TCK project plan
Build TCK development team
Draft legal documents
Community Draft Stage
“Building the TCK Phase” on page 28
Train TCK development team
Update specification mark-up
Write the tests
Begin work on TCK documentation
Create the test framework
Run TCK against preliminary RI
Public Draft Stage (Public Review cycle)
“Completion Phase” on page 30
Update specification mark-up
Complete the TCK
Complete the TCK documentation
Run TCK against final RI
Public Draft Stage (final approval cycle)
“Maintenance Phase” on page 32
Appeals are processed
Exclude list is kept up to date
TCK bugs are corrected
Release and Maintenance Stage
Chapter 1 Developing a TCK—Introduction 9
Sun’s Java Compatibility Test Tools
Sun provides the Java Compatibility Test Tools (Java CTT) that you can use to help
develop your TCK. While there may be some portions of your test framework that
cannot be provided or built using the Java CTT, using some or all of these tools and
resources will help you reduce TCK development time and improve the quality of
your TCK. These tools also help measure TCK coverage and quality and thus help
track the progress of TCK development.
Sun recommends using these tools to build the core elements of your TCK—
particularly in cases where you plan to integrate your JSR with an existing
technology in the future. Using common tools will significantly lower the cost of
such test suite integration.
The purpose of the Java CTT is to simplify conformance test development and
make developing tests and running the tests more efficient. This becomes critical
when multiple companies contribute tests to a TCK.
Chapter 3, “Using Java CTT to Build a TCK,” describes how these tools and
resources can be used together to reduce the time and resources it takes to develop
a quality TCK.
The Java CTT includes the following:
JavaTest harness. Configures, sequences, and runs test suites. The JavaTest
harness is designed to provide flexible and customizable test execution. It
includes everything a test architect needs to design and implement tests for Java
technology specifications.
JavaTest Architect’s Guide. Describes the JavaTest harness and how to integrate
your tests and the JavaTest harness into your TCK.
Spec Trac Tool. Simplifies the process of tracking assertions within a
specification as they change over time, allows test developers to quickly identify
assertions in the specification that are candidates for required testing, and
provides an assertion ID to bind to a test. The tool provides assertion coverage
reports and lists of specification assertions that are, and are not, tested by the
TCK. The tool also helps track changes in assertions, and thus helps track tests
that need to change as a result of specification revisions.
The Spec Trac Tool is designed to handle specifications that are created with the
Javadoc™ software application that is included as part of Sun’s J2SE SDK™.
Spec Trac Tool Users Guide. Describes how to install and use the Spec Trac Tool.
Signature Test Tool. This tool has two parts:
Signature file generator that identifies all public and protected members in
an API and lists them in a signature file that it creates.
10 TCK Project Planning and Development Guide August, 2003
Signature test that can be included in your TCK to verify that each member
in the signature file exists in the API under test. The signature test is used to
ensure that the entire API is present—no more and no less—than that
identified by the specification.
The Signature Test Tool also checks that the set of superclasses and
superinterfaces of a given class or interface, the set of exceptions thrown by a
given method or constructor, and the presence of the volatile modifier for a
given field, match the specification.
Signature Test Tool Users Guide. Describes how to install and use the Signature
Test Tool.
Java API Coverage Tool. Measures the percentage of public API members (that
is, the public methods, constructors, and fields) directly referenced by the TCK
tests and compares them to the total number of public API members defined by
the specification. In other words, it gives the percentage of API members that are
“touched” by the TCK tests. In addition, this tool lists the uncovered public API
members per class.
The Java API Coverage Tool is a static code analysis tool that uses a signature
file representation of the specification's API as the source for its analysis.
Another use of this tool is to identify API members that are not “touched” by the
TCK tests. This can be useful when searching for missing coverage within
critical functionality areas of a specification.
Java API Coverage Tool Users Guide. Describes how to install and use the Java API
Coverage Tool.
TCK Project Planning and Development Guide (this book). Provides an
overview and starting point for the Specification Lead and Expert Group
members responsible for developing a Technology Compatibility Kit (TCK)
under the Java Community Process program. It is a high-level planning guide
for the Spec Lead, TCK architect, and project managers.
TCK Project Plan Template. Provides an editable outline and template that can
be used as the basis for creating a written TCK Project Plan based on IEEE
standards and this TCK Project Planning and Development Guide.
Java Technology Test Suite Development Guide. Describes how to design and
write tests for any TCK. It also provides “how-to” instructions describing how to
build your TCK and write the tests that become your TCK’s test suite. It includes
examples of testable and non-testable assertions and the applicable test code.
Java Technology Compatibility Kit Users Guide Template. Provides an
editable outline and template that can be used as the basis for creating a user’s
guide for a TCK. The template can be edited to provide the basis of the user
manual that tells your customers how to use the TCK you are developing. The
template is available in Adobe FrameMaker, Adobe Acrobat, and ASCII plain-
text formats.
Sample TCK. Provides a collection of tests that demonstrate TCK test
development techniques, and illustrate particular test development issues. These
tests can be used by test developers as models and examples of how to write
their own tests.
Chapter 1 Developing a TCK—Introduction 11
The Sample TCK is a complete TCK that complements the Java Technology Test
Suite Development Guide, Spec Trac Tool, and Signature Test Tool. It includes a
Java API specification and a RI. It is run using the JavaTest harness.
12 TCK Project Planning and Development Guide August, 2003
13
CHAPTER
2
Components of a TCK
The following sections describe the components of a TCK as defined by the JCP
process. Except for the TCK planning documents, all of the other components are
delivered to your customers:
TCK Planning Documents
Conformance Rules
Appeals Process
Exclude List
Tests and the Test Suite
Test Framework
TCK Documentation
Audit Process (Optional)
TCK Planning Documents
Once the Java technology specification is drafted, the first TCK components to be
developed should be the TCK planning documents which are for your internal use.
These plans form the basis for developing the subsequent components that are
delivered to customers. The following documents are recommended:
Project plan. Provides a comprehensive description of the TCK as a product.
Test plan. Describes what needs to be tested and how that is to be accomplished.
Test integration plan. Describes how individual tests are incorporated into the
test suite.
Test specifications. Describe what each test does and the expected results.
Documentation Plan. Describes the documentation that will be written for the
TCK.
QA Plan. Describes how the TCK will be tested against the RI and the
specification.
See Chapter 4, “Planning a TCK,” for a detailed description of these plan elements
and how to create them.
14 TCK Project Planning and Development Guide August, 2003
Conformance Rules
Conformance rules define the criteria a Java technology implementation must meet
in order to be certified as “conformant” with the technology specification. In other
words, they define what it means to “pass” your TCK. These rules must be clearly
documented for those who use the TCK.
Conformance rules often complement the test suite by defining additional
conformance criteria required by the specification which may be impossible, or
impractical, to check with test applications. Rules can also be used to provide
exceptions to testing criteria (for example, identifying situations where passing the
test suite is not required).
The Specification Lead, and later the Maintenance Lead, are responsible for
establishing and maintaining the conformance rules. An example set of
conformance rules can be found in the Java Technology Compatibility Kit User’s
Guide Template.
Because all implementations of a technology specification have to meet the criteria
established by the conformance rules, the rules function as an impartial, “level-
playing-field” environment for companies developing competing products. For this
reason, the rules must be written with the same kind of care given to a legal
contract or piece of legislation. The rules have to be fair, treat everyone equally, be
complete, and be comprehensible.
The common practice is to document the conformance rules in the TCK user guide,
including a definition of terms used in the rules.
Conformance rules are tailored for each specification.
Some examples of conformance rules are:
Other than test configuration files, no test source or binary may be modified in
any way.
Every required test must be able to pass on every publicly documented
configuration of a technology implementation.
The functional programmatic behavior of every binary class and interface must
correspond to its specification.
No sub-setting, super-setting, or modification of the public or protected API is
allowed except as defined in the specification.
See Chapter 2 of the “Java Technology Compatibility Kit User’s Guide Template”
for more information about, and examples of, conformance rules.
Chapter 2 Components of a TCK 15
Tests and the Test Suite
A test suite is the collection of conformance tests included in your TCK. A TCK test
suite is designed to verify that an implementation of a Java technology complies
with its specification. A TCK might have multiple test suites, each designed to test
a different aspect of the implementation.
Tests are the binaries, source, procedures, and any accompanying information that
exercise a particular feature, or part of a feature, as described in the associated
specification. Examples of TCK tests are:
Network and I/O API tests
API signature and member (constructor, field, and method) tests
Interactive GUI tests
Most tests should be completely automated, but some tests, such as GUI tests, may
require some manual intervention by the person running the test. Tests that require
some user intervention are known as interactive tests, tests that do not require user
intervention are known as automatic tests.
Ideally, every testable assertion in the technology specification should be tested.
(See Appendix C, “Measuring TCK Test Coverage,” for more information on test
coverage.)
Assertions are statements of required behavior, either positive or negative, that are
made within the technology specification. Each assertion should be tested by one
or more tests in the test suite. A single test can test more than one assertion,
however, using one test to cover multiple assertions might produce a serious
“hole” in test coverage if that test is ever excluded because of a problem with one
of its parts. Therefore, the recommended practice is to write separate tests for each
assertion.
Test Development Requirements
Tests can be automated, or require user interaction.
Most tests return either a Pass or Fail status but other kinds of status may be
permitted if allowed by the conformance rules.
If your test harness detects that a test did not run successfully—that is, the test did
not produce a pass or fail result—it should report a status of “Error.”
The following general guidelines are suggested for test development:
Tests should be written so that their pass or fail status is never ambiguous and is
clearly presented to the test user.
All tests should implement the same test interface for the test suite under
development.
16 TCK Project Planning and Development Guide August, 2003
All tests should restore the state of the system under test when the test is
completed.
In general, there should be no hard-coding of paths, time-out values, or other
hardware specific features.
No test should depend on a previous test result or action.
Individual tests should normally test a single assertion (or part of a single
assertion).
The test should report adequate and meaningful failure diagnostics.
Ideally, TCK tests are developed to exhibit the following characteristics:
Hardware and software platform independence (all tests use Java code with
native and/or platform specific code when no other means exists)
Implementation independence with no reliance on any implementation specific
API or behavior
Designed so that the tests clearly determine pass/fail status
If a specification defines optional functionality in its API, then tests should be
written to cover that optional functionality if it is implemented. The TCK should be
configurable so that the user can identify existing optional behavior and be
confident that it is tested by the TCK.
Tests are defined as “required” if they must be passed. A “non-required” test is one
that is on the Exclude List, or that tests optional functionality that has not been
implemented in the product being tested.
Test Code Conventions
Test source code should always be delivered as part of the TCK product. It is
expected that test users will need to review the test source code whenever
necessary in the course of using the TCK to debug test failures of their
implementations. For this reason it is important to follow general source code
writing conventions, such as formatting and well chosen variable names. It is also
important that the code be adequately documented and understandable by
reasonably knowledgeable users. Source code should be checked to make sure that
is does not contain rude, indecent, or vulgar method names, variable names, or
other text.
See the Java Technology Test Suite Development Guide for detailed information on tests
and the test suite.
Chapter 2 Components of a TCK 17
Appeals Process
The Specification Lead is responsible for establishing a clearly defined TCK appeals
process to address challenges to the tests contained in the TCK.
Under the JCP process, technology implementations developed for your technology
specification must pass your TCK tests in order to be certified as compliant with
that specification. Someone engaged in developing such implementations however
may wish to challenge the fairness, validity, accuracy, or relevance of one or more
of your TCK’s tests. Therefore, the JCP requires you to provide an appeals process
by which implementors can challenge TCK tests. If a test is successfully challenged
(that is, found to be invalid) through the appeals process, that test is removed from
the TCK or modified to correct the problem.
The appeals process is an escalation process managed by the Maintenance Lead, in
which challenges to conformance tests by implementors are evaluated and either
accepted or rejected. The Maintenance Lead is appointed by the Specification Lead
and is responsible for maintaining the technology specification, RI, and TCK.
The appeals process must provide a common method for implementation
developers to challenge one or more tests defined by the Specification's TCK.
The appeals process must be described in the documentation included with the
TCK.
Technology implementors do not have to pass TCK tests that have been
successfully challenged. The common practice is to list successfully challenged tests
in an Exclude List as described in the following section.
See Appendix A, “TCK Appeals Process for more information on how to create
your appeals process and the requirements that it must meet.
Exclude List
When a test is found to be invalid through the appeals process it should be
replaced or removed from the test suite.
In most cases, individual test replacement is expensive and must be coordinated
with all TCK licensees. Therefore, tests are typically removed from the test suite
until it is practical to update the entire TCK with correct and/or new tests. The
method of removing a test from the test suite is generically referred to as using an
Exclude List.”
An Exclude List itemizes tests that do not have to be run for the specific version of
the TCK being used. Implementors are not required to pass—or even run—any test
or test on the TCK’s Exclude List.
18 TCK Project Planning and Development Guide August, 2003
An Exclude List is a practical method of managing test challenges without having
to release an entire new test suite whenever an invalid test must be removed. The
recommended practice is to use a test harness that automatically identifies tests on
the Exclude List and does not run them. The JavaTest harness, for example,
provides this functionality.
An Exclude List should be associated with each version of a TCK. It is the
responsibility of the Maintenance Lead to provide, and maintain, an up to date
Exclude List for the TCK. The initial version of an Exclude List can be bundled
with the TCK, or it can be made available separately. A documented method must
be provided to TCK users for obtaining the current Exclude List. One way of doing
this is to have a web site from which an up to date Exclude List can be
downloaded. A method of identifying different Exclude List versions must be
provided so that testers can easily make sure that they are using the correct
version.
A test might be included in an Exclude List for reasons such as:
An error or ambiguity in the specification that was used as the basis of the test
has been discovered.
An error in the test itself has been discovered.
The test fails due to a bug in the tools (such as the test harness or test agent).
An implementation dependency such as thread scheduling model or file system
behavior, is identified.
Note Typically, TCK users are never permitted to alter or modify Exclude Lists
used for certification test runs. For more information about using an Exclude List
as part of your appeals process, please see Appendix A, “TCK Appeals Process.”
Test Framework
A test framework includes the supporting code and tools that are used to manage
the TCK testing process. A test framework will usually be customizable and
configurable, to meet the requirements of the TCK for any user environment.
A test framework usually consists of at least the following components:
A test harness as described in “Test Harness” on page 19
Shared test libraries (common test code used by multiple tests). For example,
code used by several tests to open a specialized network connection using a
technology or implementation specific protocol.
An optional test agent as described in “Test Agent” on page 20
Testing scripts and other test execution/management command code as needed.
Chapter 2 Components of a TCK 19
Test harness configuration capability that allows the user to specify necessary
variables (see “Test Framework Configuration” on page 21 for details).
Ideally, a TCK should provide all framework components necessary to run the
TCK. Occasionally, however, implementation-specific features of the specification
may make creating generic components impossible. In those cases, the test users
may be required to create such components themselves. For example:
Application Management Software (AMS)—which is sometimes referred to as
Java Application Manager (JAM)—on the device being tested. This is software
that resides on (or is downloaded to) the device so that it can handle and
respond to test bundles sent by the test harness.
Implementation of a communications channel between the device under test and
the host system running the test harness so that the two can communicate. For
example, some TCKs implement a communications channel using the HTTP
protocol.
Implementation-specific test components may vary widely in complexity
depending on the test environment and the test harness being used. It is up to your
licensees to provide these components as needed using whatever tools or
techniques are appropriate for their implementation.
Providing example code for such components as part of your TCK is
recommended. For example, providing the test framework components necessary
to test the RI gives your licensees a head start in creating their own components
because they can examine how your components are used to test the RI.
Note – At the present time, Java CTT does not provide specific framework code for
J2ME devices (MIDP devices, for example) or for J2EE deployments. Developing
this kind of framework can be complex. Sun hopes to provide additional assistance
and improvements in these areas in the future.
Test Harness
A test harness typically provides:
Test selection of one or more tests to execute.
Sequencing of tests, allowing them to be loaded and executed automatically.
Automated reporting capability, to minimize manual errors.
Typically a test harness runs on a test server while managing the testing process on
a target device or workstation.
The test harness must be capable of running tests on any potential target device, or
if permitted by the conformance rules, the test harness may run tests on a
computationally equivalent emulated environment or a breadboard.
20 TCK Project Planning and Development Guide August, 2003
A test harness should facilitate the task of making sure that all required tests were
run, and all of the required tests are passed for each tested configuration of an
implementation.
A test harness needs to have some way that the user can configure it and the rest of
the test framework for the test environment (hostnames, IP addresses, file and
directory locations, which tests to run, where test results are to be stored,
communications parameters, test parameters etc). See “Test Framework
Configuration” on page 21 for detailed information.
Most TCK developers at Sun run their tests using the JavaTest harness as described
in the following section.
Sun’s JavaTest Harness
TCKs developed at Sun use the JavaTest harness for test execution and test suite
management. The JavaTest harness is a Java application that runs on most
workstations and PCs.
The JavaTest harness is designed to execute tests on varying Java technology
implementations from powerful servers to small consumer and embedded systems.
The JavaTest harness provides the following functionality:
Graphic User Interface (GUI) for ease of use
Highly flexible and configurable
Robust test framework for running tests
Graphic and file-based display of test results
Failure analysis
Reporting
Test auditing
Distributed testing environment support
The JavaTest harness is one of Sun’s Java Compatibility Test Tools and is available
to Expert Groups developing TCKs. See the JCP web site: http://jcp.org for
more information.
Test Agent
A test agent is a Java application that receives tests from the test harness, runs them
on the software being tested, and reports the results back to the test harness. Such
an agent is useful when it is impractical, or impossible, to run the test harness on
the same device as the implementation under test due to memory or API
constraints.
If the technology implementation is being tested on the same machine as the test
harness, you may, or may not, need to have a separate test agent. In other words,
when the technology implementation under test and the test harness are
running on the same system, the TCK’s test harness may be able to function
without an agent. In other cases, the software you are testing may require a test
Chapter 2 Components of a TCK 21
agent even if it is running on the same machine as the test harness. In such cases
you can use a separate test agent running as an independent process on the
same machine as the test harness.
If the technology implementation under test is not running on the same machine
as the test harness, then you need to install and run a test agent on the system or
device being tested. When the agent and test harness are on different systems,
they communicate with each other over a network or other connection.
Occasionally a TCK user will want to test multiple implementations in parallel
to reduce test run times. Providing the capability in your TCK to use multiple
agents running on separate systems or devices is a good way to provide this
functionality.
A general purpose agent called JavaTest Agent is included with the JavaTest harness.
If a new application model or device communications channel is defined by the
specification or required for TCK test execution, it may be necessary to create a
custom agent for your TCK. Writing a custom agent can be a complex and time-
consuming task, so such work should be factored into your TCK project plan and
schedule.
Test Framework Configuration
In order to run TCK tests, the test framework has to be configured for the test
environment. In other words, those who use the TCK to test their implementations
have to be able to specify hostnames, IP addresses, file and directory locations,
agent usage and configuration, which tests to run, where test results are to be
stored, communications parameters, test parameters, and so on, for their
environment.
Test suites that run in many different types of environments (for example, on
different kinds of hardware and operating system platforms) generally require
more configuration information than test suites that run in more rigidly defined
environments.
The methods of configuring the test framework will vary from one TCK to another.
The JavaTest harness, for example, provides a wizard-like interface, called a
configuration editor, to interview the user about the environment in which the TCK
tests will be run. The configuration editor prompts the user through a series of
environment questions called a configuration interview to identify needed
parameters such as IP addresses. The goal of a configuration interview is to gather
information required by the test framework to determine which tests to run and
how to run them. Based on the information provided by the user during the
interview, the editor then properly configures the TCK.
If you choose to use the JavaTest harness, writing and debugging the interview is
an essential part of TCK development. Similarly, if you use some other test harness,
you have to provide some method of configuring your TCK framework.
22 TCK Project Planning and Development Guide August, 2003
TCK Documentation
TCK documentation includes a number of components as described below.
TCK User’s Guide
A TCK should have a TCK user’s guide to document the TCK. You may also need
to include a separate user’s guide for the test harness. At a minimum, a TCK user’s
guide should contain the following:
Introduction or overview of the TCK.
Description of how install and configure the tests and test framework.
Description of how to run the TCK against the RI to verify configuration.
Description of how to run and use the TCK to test a technology implementation.
Conformance rules that the implementation under test must meet.
Appeals process for handling test challenges by users.
Sun’s Java CTT includes the Java Technology Compatibility Kit Users Guide Template.
You can use this template to create your own TCK user’s guide if you wish. It is
provided in Adobe FrameMaker, Adobe Acrobat PDF, and ASCII text formats.
Test Documentation
The tests themselves must also be documented as follows:
Source code:
Individual test source code
Specialized test framework source code such as agent, examples, shared test
libraries, and so forth that can assist the user in solving test execution
problems and debugging test failures.
Test descriptions. Test descriptions are test meta data used by the test harness to
locate and run a specific test. (See the JavaTest Architect’s Guide for details.)
Test specifications. Test case specifications describe in logical terms what a test
does and the expected results. A test case specification refers to one or more
assertions that a particular test is to verify, as derived from the related API
specification.
Release Notes
Release notes are typically provided in HTML or plain ASCII text format and
usually include some or all of the following information:
Chapter 2 Components of a TCK 23
Product Description
Produce specifications
New Features (if this is an update to an existing TCK)
System Requirements
Release Contents
Installation instructions
Usage Notes
Accessibility Features
Known Bugs and Issues
Audit Process (Optional)
As an option, a formal audit process may be used to better ensure the integrity of a
consistent self-certifying conformance testing program.
An audit can be accomplished through:
Physical testing. This is often impractical and usually quite costly due to
differences in hardware and/or operating systems that could be used to support
the implementation under test.
Test results verification.
If a test results verification program is implemented, then an independent third
party may be used to verify that all the required tests were run and have passed by
examining the test reports generated by the test harness.
The JavaTest harness supports an automated test results verification feature for use
in such an audit program.
24 TCK Project Planning and Development Guide August, 2003
25
CHAPTER
3
Using Java CTT to Build a TCK
This chapter describes how to develop a TCK using the Java CTT package of tools,
documents, samples, and templates. It contains the following sections:
Creating a TCK—Overview
Preparation Phase
Building the TCK Phase
Completion Phase
Maintenance Phase
The steps and task sequence presented in this chapter assume you are using the
Java CTT. These steps are recommended by Sun as the most cost-efficient way to
develop a TCK. However, so long as you meet the requirements mandated by the
JCP, you can develop your TCK however you wish.
Note The Java CTT can be used to efficiently develop much of the software
required for your TCK. However some portions of the test framework such as
application management software or communications protocols may be specific to
a given technology implementation and/or test environment and outside the
capabilities of the supplied Java CTT framework code. Therefore such functionality
may have to be developed independently by you using other tools or techniques.
Depending on your implementation or test environment, this may require
significant development resources.
Creating a TCK—Overview
For ease of discussion, the process of creating a TCK is broken up into four phases
keyed to the stages of creating a new JSR described in the JCP: Process Document.
This recommended TCK development sequence is summarized in TABLE 1 on
page 8.
26 TCK Project Planning and Development Guide August, 2003
While the sequence and timing of how you create your TCK is up to you, Sun
recommends that you follow the timeline presented in this guide. If your TCK
development does not proceed in sync with the corresponding JCP steps for
specification creation, you risk being caught at the end of the process with a delay
in final approval of the specification because your TCK is not ready.
Preparation Phase
Preparation for TCK development usually gets underway after the first draft of the
preliminary specification is written, and before it is submitted to the JCP for
Community Review.
Sun recommends the following preparation steps:
1. Download the Java CTT components.
Go to the JCP web site (http://jcp.org/en/resources/tdk), click through the
Java CTT Evaluation License Agreement (or sign the Redistribution License
Agreement), and then download the tools.
Java CTT Evaluation License Agreement allows you to download and use the
Java CTT for evaluation purposes.
Java CTT Redistribution License Agreement allows you to include Java CTT
components such as JavaTest harness and Signature Test in the TCK that you
deliver to your customers.
2. Develop the expertise you will need to manage a TCK project.
Building a TCK is a complicated endeavor. Thoroughly understanding all aspects
and requirements before commencing work will save both time and money in the
long run. TCK managers should familiarize themselves with the following:
The JCP: Process Document (http://jcp.org) for the specification development
timeline-sequence required by the JCP.
This TCK Project Planning and Development Guide to understand the overall scope
and process of TCK development, and to provide a basis for estimating the time
and resources you will need.
According to their various roles, different members of your TCK development team
need to be familiar with different Java CTT documents. FIGURE 2 below illustrates
the relationship, and target audiences, of the full Java CTT documentation set. For
example, this TCK Project Planning and Development Guide is intended for
Specification Leads, TCK architects, and program managers; while the Java
Technology Test Suite Development Guide is written for those who create and test TCK
tests.
Chapter 3 Using Java CTT to Build a TCK 27
FIGURE 2 Java CTT Documentation Set and Target Audiences
3. Evaluate the Java CTT package of tools, templates, samples, and documentation.
Look over, and try out, the Java CTT. This evaluation will help you decide if it will
be of assistance to you in developing your TCK. (If you decide to use the Java CTT
you must sign the Java CTT Redistribution License Agreement.)
4. Mark up the first draft of your specification.
Both TCK planning and test creation are based on the testable assertions in your
specification. Therefore, your first actual TCK development task is to identify your
specification assertions and classify them appropriately. This process is called
specification mark-up.
Specification mark-up is an on-going process as the specification goes through
revisions to incorporate feedback from the different review processes. Since these
revisions change the specification assertions, you need to regularly update the
mark-up to ensure that all assertions are correctly classified.
Sun’s Spec Trac Tool is designed for this purpose. The recommended practice is to
use Spec Trac Tool for specification mark-up, measuring how adequately your tests
cover the specification, and tracking changes in the specification over time.
5. Create your TCK project plan.
Once you have marked up your draft specification, you have an idea of how many
testable assertions it contains. That is one of the key factors in estimating the time
and resources needed to create your TCK.
A TCK project plan specifies the TCK coverage goals, overall test architecture and
design, resources needed to complete the project, tools to be used, how it will be
tested and delivered to customers, the development schedule, personnel
assignments, and so forth.
For detailed information, see:
TCK architect
(others)
Test developer
Technical writer
TCK Project
Planning &
Dev. Guide
Spec lead
TCK architect
Project manager
(others)
Test developer
Java CTT
Tools User’s
Guides
JavaTest
Architect’s
Guide
Java
Technology
Test Suite Dev.
TCK User’s
Guide
Template
28 TCK Project Planning and Development Guide August, 2003
Chapter 4, “Planning a TCK,” for a detailed description of the planning process
and help in estimating the resources you will need for test development.
Appendix B, “TCK Project Planning Questions,” for information on the
questions that various TCK planning documents need to address.
See also the TCK Project Plan Template available at:
http://jcp.org/en/resources/tdk.
6. Begin building your TCK development team.
Now that you have an estimate of the scope of the task, you can begin forming the
TCK development team.
See “Team Personnel” on page 38 for information on the different roles involved in
TCK development and “Resource Estimates” on page 39 as an example of how to
estimate time and personnel requirements.
7. Draft your license terms and appeals process.
Before you can submit your draft specification for Community Review under the
JCP process, you must draft your proposed licensing terms for both the TCK and
the RI, and your proposed TCK test appeals process.
See the JCP: Process Document (http://jcp.org) for details.
Building the TCK Phase
TCK development can begin as soon as the first draft of the specification is written.
However, as a practical matter, many developers prefer to commence TCK
development only after the specification has been revised based on feedback (if
any) from the Community Review.
Regardless of when TCK development starts, the common—and recommended—
practice is to have the TCK framework development close to complete, and test
development well underway, by the time your specification is submitted to the JCP
for Public Review. If your TCK development is not far along by that point, release
of your specification may be significantly delayed because the JCP Executive
Committee will not vote final approval for a specification until the TCK is
completed and the RI passes.
Sun recommends the following steps:
1. Train the TCK development team (if necessary).
Developing TCK tests and creating the test framework is highly specialized work.
If your developers have not had prior experience in this area, devoting some time
to training them at the beginning of the project is a cost-effective way of saving
time and money in the long run.
Suggested training might include having your developers:
Chapter 3 Using Java CTT to Build a TCK 29
Familiarize themselves with Java Technology Test Suite Development Guide and
work through the various exercises it contains.
Familiarize themselves with Part 1 of JavaTest Architect’s Guide.
Work through the JavaTest Architect’s Guide tutorial and the chapter that
describes creating a simple test suite.
Set up and run the Sample TCK that is included in the Java CTT.
Review test sources, signature test, and coverage files contained in the Sample
TCK.
2. Update the specification mark-up (if necessary) and generate a new assertion list.
Since TCK test development is based on the testable assertions in the specification
it is essential that you work at all times from a complete and up to date assertion
list. If the specification has changed since the last time you classified its assertions,
you need to do so again.
Spec Trac Tool has the capability to track and report specification changes. (See Spec
Trac Tool Users Guide for details.)
3. Begin designing your tests and writing the test specifications.
Your tests have to be designed to test implementations for conformance with
specification assertions.
See Java Technology Test Suite Development Guide for further information.
4. Include the signature test in your TCK.
See Signature Test Tool Users Guide for further information.
5. Begin designing and creating your test framework.
Your test framework will need a test harness and possibly one or more additional
components:
Test harness.
JavaTest interview (if you are using JavaTest harness).
Test finder or finders.
Test agent. (The JavaTest harness includes the Java Test Agent that you can use,
or you may need to write your own custom agent.)
Test script or scripts.
Exclude List (which can be empty).
Other framework components as might be needed. (Depending on the specifics
of your implementation, additional framework components may require
extensive development work.)
6. Integrate your tests with the test harness.
See JavaTest Architect’s Guide for general information about designing and building
test frameworks, and JavaTest Users Guide for information about the JavaTest
harness.
30 TCK Project Planning and Development Guide August, 2003
7. Begin testing and de-bugging your tests and test framework.
If you have a stable Reference Implementation (RI) available, run your tests against
the RI to find and correct problems. (Lack of an RI at this stage will delay your
overall specification development because your specification cannot win final
approval until you have a completed TCK and an RI that passes all of your TCK
tests.)
Run the TCK against the RI to check for, and correct, problems with both the tests
and the test framework. Note that a test could fail for one of two reasons. A valid
test could fail because there is a problem with the RI (that is, the RI does not
correctly implement the specification or meet a conformance requirement). Or, if
the RI is correct, the test could fail because of some bug or error in the test itself.
8. Produce preliminary TCK reports.
Once you have a working TCK and RI, you should begin producing the following
reports to check and evaluate your progress:
Test run results showing that the RI has passed (or failed) the individual tests.
Assertion coverage reports generated by Spec Trac Tool.
API coverage reports generated by Java API Coverage Tool.
9. Begin work on the TCK Users Guide
See the Java Technology Compatibility Kit User’s Guide Template for more
information.
10. Update your TCK Project Plan.
Keeping your TCK Project Plan up to date as the work evolves is a useful—and
cost-effective—management tool.
Completion Phase
Your TCK (and RI) must be completed before you can submit your final
specification to the JCP Executive Committee for final approval ballot. The
specification will not be approved unless the TCK can be run against the RI with no
test failures.
Sun recommends the following steps:
1. Update the specification mark-up (if necessary) and generate a new assertion list.
If the specification has changed you need to ensure that your TCK development is
based on a complete and up to date specification mark-up and assertion list. To do
this you should run the Spec Trac Tool’s specdiff and track commands.
2. Complete your TCK including the test framework.
Make sure that:
Chapter 3 Using Java CTT to Build a TCK 31
All TCK tests can be run against the RI without failure and the RI meets all
testing requirements.
Your test suite meets the coverage criteria targets set forth in your TCK Project
Plan. Assertion coverage can be measured by the Spec Trac Tool and method
coverage by the Java API Coverage Tool.
Your test framework includes all the components and example code (if
necessary) for your customers to test their implementation in the appropriate
environments.
Your Exclude List is up to date and accurate.
The redistributables that you will be delivering to your customers are correctly
packaged and ready to go.
3. Put your TCK through a formal QA test program.
As with any other software delivered to your customers, your TCK should be
rigorously tested in a formal QA program.
4. Complete your TCK documentation.
Make sure that your documentation set includes the following:
An adequate and comprehensible TCK User’s Guide describing how to install,
configure, and use your TCK.
The Conformance Rules that your customer’s implementations have to meet.
An appeals process that customers can use to challenge TCK tests.
Test harness documentation, if needed.
Release Notes (or Readme file) as needed.
5. Run your TCK against your RI to produce your final reports.
To ensure that your TCK and RI meet the quality standards set forth in your Project
Plan, you need to compare the final reports to your plan goals. For example, with
the Java CTT, you would generate the following reports:
Final test-run reports from the JavaTest harness showing that the RI passed all of
the TCK tests.
An assertion coverage report generated by the Spec Trac Tool.
An API coverage report generated by the Java API Coverage Tool.
6. Prepare for TCK and RI delivery to your customers.
Make ready, and test, whatever methods you will use to deliver your finished TCK
and RI to your customers. For example, you might have your customers download
your TCK and RI from a web site. (Be sure you have signed the Java CTT
Redistribution License Agreement.)
32 TCK Project Planning and Development Guide August, 2003
Maintenance Phase
The specification maintenance phase begins after your specification has won final
approval from the JCP Executive Committee and it has been posted to the JCP web
site as a final release. The maintenance phase includes the following:
A Maintenance Lead (ML) is designated.
The ML responds to test challenges (if any) and manages the appeals process as
described in your TCK documentation.
The ML maintains and keeps the Exclude List up to date.
The ML keeps track of suggested or proposed changes that might be included in
some future release of the specification, RI, or TCK.
33
CHAPTER
4
Planning a TCK
This chapter describes a recommended TCK planning process that will help you
scope out and organize the development of your TCK. It contains the following
sections:
Initial Questions
Initial Decision Points
TCK Plans
Team Personnel
Resource Estimates
Developing a TCK is a large and complicated task, but working through the basic
planning steps discussed in this chapter can simplify the process and save
significant time and human resources during the course of the development cycle.
These guidelines will also help you estimate the time and resources needed to
complete the project. The procedures contained in this chapter are written for large,
complex TCKs. If your TCK is smaller, you may wish to simplify, or omit, some of
these steps.
You can use the TCK Project Plan Template which provides an outline, instructions,
and some boilerplate that can be used as the starting point for writing TCK plans.
The TCK Project Plan Template is available at:
http://jcp.org/en/resources/tdk.
Initial Questions
The first step in planning a TCK is to consider the initial questions that have to be
addressed before you begin planning. You have probably already thought about
most or all of these questions, and it is not necessary at this stage to have complete
detailed answers to every one of them, but listing them here will make your
planning process easier.
34 TCK Project Planning and Development Guide August, 2003
Does your specification define its own application model?
An application model is the method used for downloading an application into a
particular device. It must include the definition of a specific Java class or
interface, a method of which is called by the runtime environment as the first
method to run when the application starts. Some examples are:
The default application model described in JVMS
Applets in J2SE
Midlets in MIDP
Xlets in Java TV
Java Card Applets in Java Card.
In regards to planning your TCK, your answer to this question determines
whether you can use a pre-existing test framework that supports this application
model (such as the JavaTest Agent and test framework code supplied with
JavaTest harness), or whether you will have to write your own.
How many testable assertions does your specification define?
The number of testable assertions is directly related to the number of tests you
have to write, and thus can be used to estimate the overall size of your TCK and
the time and resources you will need to complete it.
Sun recommends using Spec Trac Tool to classify and track the testable
assertions in your specification.
How many API members does your specification define?
While not as precise as the assertion count, it is often much easier to estimate the
number of API members which for most APIs is also related to the number of
tests you will need to write, and thus can be used to estimate the overall size of
your TCK and the time and resources you will need.
Sun recommends using the Java API Coverage Tool to identify, count, and track
your API members.
Do you have APIs that require functional tests?
This question distinguishes between two kinds of tests:
API member tests (sometimes referred to as class and method tests) are designed
to verify specific semantics of individual API members. (See Java Technology
Test Suite Development Guide for more information about class and method
testing issues.)
Functional tests are designed to verify higher level functionality supported by
a specification, often as a result of cooperation among multiple API members.
For TCK planning purposes, the distinction between these two kinds of tests is
important because member tests are usually simpler and easier to write than the
more complex functional tests, but functional tests may be needed for effective
coverage of the specification.
Chapter 4 Planning a TCK 35
For example, with functional tests:
The visual behavior of graphical user interface (GUI) components may
require interactive testing because the test user has to determine whether the
components are visualized correctly. (By comparison, the simple pass-fail
status of API member tests can usually be determined automatically by the
test itself.)
Tests for network protocols may require running different components of the
tests in different runtime environments on different network hosts.
Serial form testing for serializable classes have to verify that the serializable
object can be correctly serialized and deserialized and verify the serial form
stream against the specification.
Functional testing is typically implemented using object libraries (frameworks)
that contain the TCK code common to the specific area of functional testing.
These libraries have to be written or otherwise obtained.
If your specification contains many APIs that require functional tests, your TCK
test suite will be more complex and take longer to write. Libraries may also have
to be created to support them. And, of course, your QA process of de-bugging
the tests will also take longer.
Does your specification have methods/APIs that can return different values
depending on different environments, or on different implementations of the
specification?
For example:
java.util.Locale.getAvailableLocales() may return different
values depending on what locales are supported by this particular
implementation.
java.util.Date.toString() may return different strings depending on
the time zone settings of the underlying OS.
The more implementation-dependent values contained in your specification, the
more configurable your TCK has to be to accommodate different environments
and implementations, and that makes your tests more complex. This can affect
the time required to develop the tests and the TCK as a whole because the
design of your TCK has to take into account this configurability.
How likely it is that the specification will be revised multiple times?
Is this an API for a well-known stable technology or is it an API for a technology
that is undergoing extensive changes during TCK development? If the API is
evolving rapidly, individual tests may have to be added or updated and the TCK
as a whole may have to be reworked in the middle of its development cycle.
When planning time lines and schedules, these possibilities need to be taken
into account.
If the specification is undergoing changes, you should consider using the Spec
Trac Tool to track and monitor assertion changes to help identify the associated
impacted tests.
36 TCK Project Planning and Development Guide August, 2003
How complex is the data structure represented by the API?
For example, is it relatively easy to get an instance of a class/interface to test or
do you have to go through a long chain of API calls to obtain an object to test?
API complexity affects the length of time it takes to write your TCK tests. The
more complex the API, and the more calls required, the longer it will take to
write and debug the test.
Are there any aspects of application or data delivery that are intentionally not
defined by the specification but left to the implementation?
For example, CLDC does not require any specific type of connectivity to be
present. Nor does Java TV, where the way of delivering broadcast data to the Set
Top Box is device-dependent.
If there are undefined aspects left to the implementation, your TCK may have to
be designed to leave implementation of some parts of the test execution
framework to TCK users. Not only is this a design and coding issue, it also
makes TCK debugging more difficult because you have no control over whether
the user-created code functions correctly.
Initial Decision Points
There are several key decisions that need to be made before you can develop your
plans:
Assertion coverage. What is the overall amount of assertion test coverage
desired for your API? Obviously, the greater the coverage, the more tests you
will require, and the more time and resources you will need to develop and
debug your TCK. The best practice is to strive for at least 75%assertion breadth
coverage.
See Appendix C, “Measuring TCK Test Coverage,” for more information on test
coverage.
API Coverage. Assertion-based testing is the most accepted means to check an
implementation for conformance. Therefore, TCK completeness is normally
defined by the amount of its assertion coverage. API member coverage,
however, can provide an additional means for measuring the completeness of a
TCK. What amount of member coverage (that is, direct references by tests to
public methods, constructors and fields) is desired for the public API’s defined
by your specification? The recommended practice is to try to provide at least
90% API coverage.
Test harness. Which test harness will you use? You can use the JavaTest harness
that Sun provides as part of the Java Compatibility Test Tools (Java CTT), or you
can use another test harness.
(Note that the “Resource Estimates section of this chapter assumes that you are
using the JavaTest harness.)
Chapter 4 Planning a TCK 37
Test agent. If using the JavaTest harness, will you need a test agent as described
in “Test Agent” on page 20? If so, will you be using the JavaTest Agent provided
with the JavaTest harness, or will you be writing your own test agent?
Java CTT tools. Will you be using the Java CTT tools that are described in
“Sun’s Java Compatibility Test Tools” on page 9?”
(Note that the “Resource Estimates” section of this chapter assumes that you are
using the Java CTT.)
TCK Plans
Once your preliminary specification is drafted and your initial decisions made, you
need to draft the plans for your TCK. These plans form the basis for developing the
subsequent components that are delivered to your customers. Experience has
shown that careful TCK planning at the start of the project saves time and money
in the long run.
You can use the TCK Project Plan Template which provides an outline, instructions,
and some boilerplate that can be used as the starting point for writing TCK plans.
The “TCK Project Plan Template” is available at:
http://jcp.org/en/resources/tdk.
Conceptually, there are a number of different elements that go into a set of TCK
plans:
Overall TCK Project Plan. Provides a comprehensive description of the TCK as
a product. (See “TCK Project Plan” on page 47 for some of the questions that the
overall project plan should address.)
Keep in mind that developing and delivering a TCK to customers is more
complex than writing testing software to be used internally in-house. See
“Conformance Testing vs. Product Testing” on page 5 for more information on
this issue.
Preparation Plan (if needed). Describes what preparations (if any) are needed
before TCK development work can begin. For example, research, prototyping,
developer training, acquisition of hardware or tools, creation of infrastructure,
and so on. (See “Preparation Plan” on page 48 for some of the questions that this
plan should address.)
TCK Design Document. Describes what needs to be tested and approaches for
how testing will be accomplished. This document also describes how the
individual tests are incorporated into the test suite, and how the test suite is
integrated with the test harness. (See “TCK Design Document” on page 48 for
some of the questions that this document should address.)
Test Specifications. Describes what each test does and the expected results.
Typically, these test specs are also included with the tests, or as part of the TCK
documentation, so that they are available to test users. In other words, this
38 TCK Project Planning and Development Guide August, 2003
component is both part of the plan, and part of your TCK documentation. (See
“Test Specifications” on page 49 for some of the questions that this document
should address.)
Documentation Plan. Describes the documentation that will be written for the
TCK. (See “Documentation Plan” on page 50 for some of the questions that this
plan should address.)
QA Plan. Describes how the TCK will be tested as a product to be delivered to
customers. (See “QA Plan” on page 51 for some of the questions that this plan
should address.)
If your planning information is not very complicated or lengthy, some or all of the
above elements can be combined into the same document.
See Appendix B, “TCK Project Planning Questions,” for a list of questions that
these different plans should address.
Team Personnel
A TCK development project contains within it a number of different roles. While
one person can perform multiple roles, it is useful for planning purposes to think
of the roles separately:
Specification Lead. Heads the Expert Group and is responsible for overseeing
all aspects of developing (or revising) a Java technology specification. This
includes development of the Reference Implementation (RI) and Technology
Compatibility Kit (TCK).
Maintenance Lead. Responsible for maintaining an existing technology
specification and related RI and TCK. Manages the TCK appeals process and any
revisions needed to the specification, TCK, or RI.
Program Manager. Because your specification has to be developed using the JCP
procedures, someone needs to be responsible for ensuring that your specification
development meets the JCP requirements in a timely manner.
TCK Architect. Leads the TCK development team and designs the overall test
architecture and testing framework. Lists, or oversees the identification of
specification assertions that need to be tested and the corresponding test
specifications. Determines how the tests and test suite are integrated with the
test harness.
Test Developer. Writes the individual tests and implements the testing
framework (as needed). Debugs test problems. If the JavaTest harness is being
used, writes the test harness configuration interview.
Quality Assurance Engineer. Tests the TCK and documentation for accuracy,
functionality, completeness, and performance.
Chapter 4 Planning a TCK 39
Technical Writer. Writes the TCK user guide and release notes. Works with a test
developer to edit or revise the language of error messages and the test harness
configuration interview. Helps to edit or revise the language of test
specifications for readability.
Resource Estimates
The time it takes to complete your TCK depends on many factors specific to your
technology and your TCK. Obviously, the scope of the TCK, the number of tests,
the number of people you have working on it, the optional components, the tools
you are using, and many other factors affect your schedule. There may also be
specific platform limitations such as a small screen, memory limitations, or absence
of a guaranteed way to perform some input on the device, that affect the time it
takes to develop your TCK.
To assist your planning, time estimates based on TCK development experience at
Sun are presented below. These estimates are given only for the purpose of
illustrating a time-estimation method, your own development metrics and time
lines will certainly vary.
As an initial general estimate, the experience at Sun indicates a rough equivalency
between the time needed to develop the specification RI and the TCK. In other
words, for every engineer-day spent on developing the RI, an engineer day is
needed for the TCK.
4.5.1 Time Estimate Assumptions
The example TCK development estimates in the following sections are based on the
following assumptions:
The TCK is developed using the Java Compatibility Test Tools (Java CTT),
including the JavaTest harness, as described in “Sun’s Java Compatibility Test
Tools” on page 9.
Few functional tests are required. Most tests are API member tests.
The specification has few methods or APIs that return different values
depending on different environments, or on different implementations of the
specification.
The specification is not changing so rapidly that a significant number of tests
have to be re-written in the middle of the development cycle.
The API is not so complex that you have to go through a long chain of API calls
to obtain an object to test.
40 TCK Project Planning and Development Guide August, 2003
Time Estimates—Test Development
The largest single component in TCK development is writing the TCK tests.
Obviously, the number of needed tests is governed by the quantity of packages,
classes, methods, constructors, and fields in the API being tested and amount of
specification assertion coverage desired.
The following test development time estimator may be useful in identifying the
scope of effort required to build your test suite. This is based on experience within
Sun for experienced TCK test development engineers. Your experiences will no
doubt vary:
(A-Num
× CovBreadth ÷ DevRate) × NumEng = Test Development Time (in weeks)
Where:
A-Num is the number of testable assertions defined by the specification.
CovBreadth is the coverage breadth goal. For example, 0.75 for 75% breadth
coverage.
(Note that the ideal practice is to thoroughly test all elements which requires
100% breadth and depth coverage. Assertion breadth coverage of only 75%
means that assertion testing is incomplete.)
DevRate is the test development rate. According to Sun's experience a typical test
development rate is approximately 12.5 test cases per week for a test developer
to write, document, and debug assertion test cases (including simple test
framework development).
NumEng is the number of engineers writing tests.
Tip: If A-Num is not known, a rough approximation for A-Num can usually be
estimated by multiplying the total number of public API members (in other words,
all public methods, constructors, and fields) defined in the specification by 3. So if
you have 1000 such public API members, you would estimate roughly 3000 testable
assertions.
Using an A-num of 3000, a CovBreadth of 75%, and the estimated DevRate of 12.5 test
cases per week per engineer, the above formula would return 180 weeks for test
development time:
(3000 × .75% ÷ 12.5) = 180 engineer-weeks
If you had 10 engineers writing and debugging tests, your test-development
schedule would be 18 weeks.
Additional tests may also be needed for non-API features of the specification. This
occurs when testing simple method, constructor, and field functionality is
insufficient to fully verify the requirements of the specification. For example,
functional testing may be needed to verify complex interactions between certain
API members and classes. Estimating the number of such tests is difficult and
highly dependent upon your specification.
Chapter 4 Planning a TCK 41
Time Estimates—Other TCK Elements
Test writing is just one aspect of developing a full TCK. Time estimates for other
aspects must be included as well:
Reasonable time allotment for training the team to be able to properly read the
specification and understand the testing environment needs to be added,
typically: 1-2 months for a new engineer and 1-2 weeks for an experienced TCK
test developer.
Up to 25% of the estimated test development time should be included in your
estimates for fixing bugs found by Quality Assurance evaluation of the TCK
against the RI. This includes the time it takes to re-work tests invalidated by
minor changes to the specification during the period of TCK development. QA
testing can usually begin after the first stable build of the TCK.
Two to four weeks for final QA approval of the TCK following completion of the
test suite should also be included.
While the test development estimation technique described above includes
allowances for some simple test framework development, any major test
framework requirements must be planned as well. For example, time and
resource estimates should be included for:
Complex shared test library classes
Configurable test framework infrastructure (if needed) as well as any other
code, examples, and/or tools necessary for the user to adapt the test harness
to their own testing environments.
Writing and testing the means your customers will use to configure the TCK
for use in their environment. For example, if you are using the JavaTest
harness, the configuration interview questions and “more information”
explanations have to be written, integrated, and tested.
Writing and testing a test agent and/or Java application manager if either are
needed. (Note that Sun provides the JavaTest Agent that can be used as-is in
many cases.)
Time and resources must also be allocated to the development of the project
build environment, such as writing makefiles, promoting and archiving builds,
etc. This may vary significantly across different TCKs and development
environments.
Documentation time should be estimated for writing the user's guide, release
notes, and working with the engineers on the test specifications (and a JavaTest
harness configuration interview if one is used). Note that using the “Java
Technology Compatibility Kit User's Guide Template” may significantly cut the
time required to write your TCK user's guide.
Reasonable time allotments must be added for several QA and development
engineers to review the TCK documentation. It is suggested that they read and
comment on at least two drafts of each document.
Also plan for any additional time that may be required if the specification
changes markedly during the period of TCK development, or if stable RI builds
are unavailable for testing and debugging the tests.
42 TCK Project Planning and Development Guide August, 2003
43
APPENDIX
A
TCK Appeals Process
This appendix describes the TCK appeals process, it contains the following
sections:
Introduction
Appeals Process Guidelines
Test Appeal and Response Forms
Introduction
Under the JCP process, implementations of your technology specification must
pass your TCK tests in order to be certified as compliant with that specification.
Someone engaged in developing an implementation, however, may wish to
challenge the fairness, validity, accuracy, or relevance of one or more of your TCK’s
tests. Therefore, the JCP process mandates a two-stage appeal process:
1. First-level appeal. The first-level appeals process allows those who are
developing implementations of a technology specification to challenge one or
more tests defined by the TCK. It is the responsibility of the Specification Lead
to establish and determine how the first-level appeal process works. The details
of the first-level appeals process must be described in your TCK documentation.
Once the appeals process is established and the technology specification
released, challenges are managed by the Maintenance Lead.
2. Second-level appeal. The second-level appeals process is mandated and
managed by the appropriate Java Community Process Executive Committee
(EC) to allow technology implementors who are not satisfied with a first-level
decision to appeal it to the EC itself. The procedures for a second-level appeal
are described in the JCP: Process Document
(http://jcp.org).
A second-level appeal should only be initiated in rare cases where the test
challenger and Maintenance Lead have exhausted all other means of resolving
the test issues.
44 TCK Project Planning and Development Guide August, 2003
A decision by a first or second-level appeal may require that the Maintenance Lead
update or modify the TCK and/or the RI.
Appeals Process Guidelines
The first-level appeals process must be designed by the Specification Lead with
assistance from the Expert Group to resolve TCK test challenges in a timely
fashion.
At a minimum, a first-level appeals process should answer the following questions:
Who can make challenges regarding the TCK?
What kind of challenges to TCK test may be submitted? In other words, what
are legitimate grounds for challenging a test? For example, some or all of the
following might be considered as valid challenges to a test:
The test has bugs (for example, program logic errors).
The specification assertion covered by the test is ambiguous.
The test does not match the specification.
The test assumes unreasonable hardware and/or software requirements.
The test is biased for or against a particular implementation.
What kind of challenges to TCK test are not accepted? In other words, what
kinds of challenges are normally rejected? For example, challenges based upon
issues unrelated to technical correctness, or challenges questioning the value of
well defined specification features, may be rejected out of hand as inappropriate.
How, and to whom, are these challenges submitted? What steps must someone
take to challenge a TCK test?
How, and by whom, are challenges decided? This might be accomplished by
giving the Maintenance Lead complete authority to interpret the specification
and rule on each test challenge, or there may be an evaluation committee, or
some other mechanism for ruling on challenges.
What happens if a challenge is accepted as valid? If using an Exclude List, how
quickly is a challenged test added to the Exclude List and how is the new
Exclude List made available to users?
Can the Maintenance Lead create an alternative tests to address any challenge?
If so, how is the alternate test made available?
An alternate test might be permitted in situations where a problem is identified
in one or more tests that are so critical to the testing process that their exclusion
would jeopardize the integrity of the TCK. In these rare cases it may be
necessary to make an alternate test available to TCK users that can be used in
place of the invalid test. In other words, a TCK user could meet the conformance
requirements by passing either the original test or its alternate. Note that
alternate tests are quick fixes to problems that should be resolved in the next
TCK release.
Appendix A TCK Appeals Process 45
The following criteria are strongly encouraged in every first-level appeals process:
All reviews for TCK challenges must follow the same process and be reviewed
by either the Maintenance Lead or one or more designees of the Maintenance
Lead.
All implementors must be treated equally in terms of access to all TCK changes
and updates including test corrections, additions and exclusions, pass/fail
reporting criteria, and conformance requirements.
See the Java Technology Compatibility Kit User’s Guide Template for an example
of a first-level appeals process.
Test Appeal and Response Forms
Using designated forms for both a test challenge and a challenge rebuttal can
facilitate the process of submitting test challenges and their related responses. The
following examples include items that these forms might contain.
Example challenge form items:
Test challenger name and company
Specification name(s) and version(s)
Test suite name and version
Exclude list version
Test name
Complaint (argument for why test is invalid)
Example challenge rebuttal form items:
Responder’s name and company
Responders role (for example, test developer or Maintenance Lead)
Specification name(s) and version(s)
Test suite name and version
Exclude list version
Test name
Defense (argument for why test is valid)
Alternatives (for example, are alternate tests appropriate?)
Implications of test invalidity (for example, other affected tests and test
framework code, creation or exposure of ambiguities in specification due to
unspecified requirements, invalidation of the RI, creation of serious holes in the
test suite, etc.)
46 TCK Project Planning and Development Guide August, 2003
47
APPENDIX
B
TCK Project Planning Questions
This appendix describes the questions that various TCK planning documents need
to address. It contains the following sections:
TCK Project Plan
Preparation Plan
TCK Design Document
Test Specifications
Documentation Plan
QA Plan
TCK Project Plan
The TCK Project Plan should normally answer questions such as:
What is being tested by the TCK?
What is the target level of test coverage that will be completed as of the product
shipment date? In other words, if there are X number of assertions and API
members, how many will be tested? At least 75% breadth assertion coverage is
recommended. (See Appendix C, “Measuring TCK Test Coverage,” for more
information on test coverage.)
What platforms will the Reference Implementation (RI) run on? Your TCK has to
run against the RI on each RI platform.
Which test harness (such as the JavaTest harness) will you use?
What other tools (such as the Java CTT) will you use?
What is the overall test architecture and design?
Is any special hardware or software needed to run the tests?
Will customers download the TCK from a web site, or will it be distributed by
CD or other hard media?
48 TCK Project Planning and Development Guide August, 2003
How will the TCK be assembled for customer delivery and installation? One
common method is to distribute the TCK as a single ZIP file archive containing
the test suite, test harness, and all associated documentation. Another possible
method is to provide an installation program.
Who is responsible for the various test development tasks?
Who is responsible for ongoing maintenance of the tests?
How long it will take to complete the TCK? (See “Resource Estimates” on
page 43.)
What are the milestones and schedule for test development and product
development?
What are the risks?
Preparation Plan
The Preparation Plan should normally answer questions such as:
What resources are required to develop the TCK test suite? In addition to human
resources, what equipment, software tools, space, support services, and other
infrastructure will be needed?
Will test suite engineers need training in conformance testing? If yes, what will
that training consist of, and what resources will be required?
What preliminary research and prototyping (if any) will be needed?
TCK Design Document
The TCK Design Document should normally answer questions such as:
Which specification assertions need to be tested? (The list of assertions is the
starting point of a test design plan.)
Are there any items that will need to be included in the API implementation
under test in order to execute the tests? For example, some special TCK related
hardware or software might be required.
Are there any issues that must be addressed due to a special TCK-related
hardware or software characteristics? For example, support of a limited number
of files or limited file name length.
What specialized test framework code must be developed (if any)?
Is a test agent needed? If yes, will you use the JavaTest Agent that comes with
the JavaTest harness, or will you have to write your own agent? If a special test
agent needs to be written, what are its requirements and parameters?
Appendix B TCK Project Planning Questions 49
Does the device being tested require Application Management Software as
described in “Test Framework” on page 18? If so, is it available or does it have to
be written? If it has to be written, what are its requirements and parameters?
Are any enhancements required for the existing test development or test
execution tools? For example, is there a need for unique or specialized hardware
due to unusual characteristics or limitations of the technology under test?
Are there any changes in the usual testing process that will be required by the
planned test suite?
What types of tests are being developed? Will they be differentiated based on
class, API functionality, or other test classification characteristics? Ideally, the
goal is to write both class-based and method/functionally-based tests for the
entire implementation of the Java technology API specification.
What test development will be proposed for the API? This needs to be described
in detail, including sources for test development methodology and completeness
measurements.
What non-API tests need to be developed? Tests of classes, methods,
constructors, and fields may not test everything in the specification that needs to
be tested. For example, you may need to include tests of the security model,
tests of how the application is deployed on a device, tests of the ways a server
and a device communicate, tests of the ways in which the device reacts to the
changes in a network environment, and so forth.
How will the tests be incorporated into the test suite?
How will the test suite be integrated with the test harness?
How will test results be verified?
How will areas of functionality to be tested be grouped into tests for the test
suite?
What performance criteria is required?
Will any standard test-library code be needed?
What resources will test development require (people, equipment, software,
facilities, support)?
For more information see “Tests and the Test Suite” on page 23 and the Java
Technology Test Suite Development Guide.
Test Specifications
Test specifications are human-readable descriptions in logical terms of what a test
does and the expected results. (If adequate test specification information can be
incorporated into the Test Design Document, then it is not necessary to develop
exhaustive test specifications for each test in the kind of separate plan discussed
here.)
50 TCK Project Planning and Development Guide August, 2003
Test specifications have a dual role. They are the plans that guide the writing of
individual tests, and they provide the documentation describing each test which
customers should receive as part of the TCK.
Therefore, in addition to describing what each test does, you may also need to
address how the test specifications are delivered to your customers. For example,
when using the JavaTest harness the recommended practice is to provide the
individual test specifications in HTML within the test suite test directory tree. If
they are straightforward and you are using HTML test description files with the
JavaTest harness, the test specifications can be located within the same HTML file
as the test description used to actually run the test; if not, test specifications can be
placed be in separate HTML files with links to the appropriate test description files.
See “Tests and the Test Suite” on page 23 for additional information on test
specifications.
Documentation Plan
The Documentation Plan should normally answer questions such as:
What documentation will be supplied with the TCK? Typically, a TCK comes
with a TCK user’s guide, test harness user’s guide, release notes, and test
specifications.
In what formats (HTML, PDF, ink-on-paper, etc,) will the documentation be
delivered?
What will be covered in the user’s guide? (Typically a documentation plan
includes a chapter outline.)
Who will review the documentation? (Remember to include documentation
review time in the reviewer’s schedule and time estimates.)
How long will it take for the documentation to be written, and reviewed?
What is the documentation delivery schedule?
Will your documents need to pass through legal or trademark reviews?
Will they be copy-edited by someone other than the author?
Will your documents comply with Section 508 of U.S. government accessibility
requirements? If so, how will that be accomplished?
Will your documents be localized? If so, to which other languages?
What resources will documentation require (people, equipment, software,
facilities, support)?
Note that as part of Java CTT, Sun provides a TCK user guide template that can be
used as the basis for your user guide if you wish. For more information see “TCK
Documentation” on page 28.
Appendix B TCK Project Planning Questions 51
QA Plan
The QA Plan should normally answer questions such as:
Are there any applicable standards used as references? For example, IEEE
standard 829-1983.
What test environment will be used?
Which, or how many, builds will be tested?
Which platforms will be tested?
What is the pass/fail criteria?
What will be tested and what testing approaches should be used? For example,
how might the following elements be tested?
System as an entire entity
Individual components
TCK performance
TCK robustness
Generation of correct error messages
Test harness integration
TCK configuration options
TCK installation procedures
TCK user guide and other documentation
How will the testing be designed and accomplished?
What testing tools are needed? Do they already exist, or do they have to be
created?
How will problems and bugs be reported, tracked, and corrected?
What are the QA testing time-line, schedule, and milestones?
What resources will QA testing require (people, equipment, software, facilities,
support)?
Testing a conformance test suite is a challenging task. While it is easy to verify that
all TCK tests pass when run against a perfect RI, it is rare to have the luxury of
“bad implementations” that can be used to trigger failures in your TCK tests.
Therefore, it is important to identify QA testing approaches to verify as much
“negative” testing as possible (in other words, creating situations that should cause
TCK tests to report failures). Some ways to do this are to purposely misconfigure a
TCK, construct RI implementations with known problems, or use specialized test
framework code that can trigger failures in API tests. These testing approaches
should be included in your QA plan.
52 TCK Project Planning and Development Guide August, 2003
53
APPENDIX
C
Measuring TCK Test Coverage
This appendix describes metrics that you may wish to use in measuring TCK Test
coverage. It contains the following sections:
Overview
Assertion Coverage
API Coverage
Signature Coverage
Overview
A Technology Compatibility Kit (TCK) is a set of tests, tools and documentation
that allows an implementor of an associated Java Technology Specification to
determine if the implementation is compliant with the Specification. To accomplish
its purpose, the TCK test suite must adequately cover the entire specification.
To assess the quality of your TCK, and to ensure that the entire Specification has
been adequately covered, Sun recommends addressing the following metrics:
“Assertion Coverage” on page 55
“API Coverage” on page 59
“Signature Coverage” on page 60
Terminology
The following terms are used in this Appendix:
API member. Fields, methods and constructors for all public classes that are
defined in the Specification.
Assertion. A specific statement of functionality or behavior derived from a
specification.
For example: from the method description for
java.lang.Integer.toString(int i, int radix):
54 TCK Project Planning and Development Guide August, 2003
If the radix is smaller than Character.MIN_RADIX or larger than
Character.MAX_RADIX, then the radix 10 is used instead
From the method description for java.lang.Integer.parseInt(Strings):
Throws: NumberFormatException if the String does not contain a
parsable int
Assertion attribute. One or more binary true/false values that are applied to an
assertion. (See “Assertion Attributes” on page 54 and TABLE 2 on page 55 for
more information.)
Test case. A single set of test inputs, execution conditions, and expected results
developed to verify an implementation’s conformance with a specific assertion.
Note that multiple test cases will often be required to thoroughly test assertion
conformance. (Equivalence class partitioning and boundary value analysis
techniques are typically used to identify suitable test cases.)
For example, the java.lang.Integer.toString assertion quoted above
would be tested by passing several different values for the radix parameter and
verifying that the specified behavior resulted. Logical groupings of values (for
example two or three between Character.MIN_RADIX and
Character.MAX_RADIX) might be applied in a single test case.
Assertion Attributes
Each of the attributes listed in TABLE 2 on page 55 are applied to every assertion.
These attributes have binary ('true' or 'false') values. Note that more than one
attribute may be true for a particular assertion.
Appendix C Measuring TCK Test Coverage 55
Assertion Coverage
This section discusses assertion coverage and the processes and metrics used to
measure it.
Process
1. Specification mark-up. You review the specification, identifying assertions and
classifying them by assigning the appropriate values to each assertion attribute.
For example, “Is the assertion testable, or ambiguous, yes or no?” Sun's Spec
Trac tool significantly aides in this mark-up process.
TABLE 2 Assertion Attributes
Attribute TRUE FALSE
Required
NOTE: Typically, optional features
are nevertheless tightly specified.
That is, implementors may be free
not to implement a feature, but if
they do so they must follow the
specification.
The functionality specified in the
assertion must be implemented.
(This is typically indicated in the
specification by use of the words
“must” or “shall”.)
Implementation is optional
(typically indicated by use of the
word “may”).
Implementation-specific
Precise details of the behavior are
deliberately unspecified; how they
are implemented is left to the
discretion of the implementor. By
definition, such behavior is
untestable for the purpose of
conformance testing.
The behavior is specified, and
therefore (in principle) is testable.
Testable
This assertion can be tested. This assertion can not be tested,
because the preconditions or the
test observation cannot be
achieved reliably or portably,
because creating or executing tests
would require an unreasonable
amount of time or resources, or
because the assertion is
ambiguous (see next attribute).
Ambiguous
The assertion is ambiguous, and
therefore cannot be tested.
(Typically this will be considered a
bug in the specification.)
The assertion is unambiguous,
and therefore (in principle) is
testable.
56 TCK Project Planning and Development Guide August, 2003
2. Assertions to be tested. You decide which assertions should be tested, and to
what level of detail. The marked-up specification should be reviewed and
approved by the Specification Lead.
It is likely and appropriate that different portions of the specification will be
tested with different levels of thoroughness. You should select for detailed
testing those portions of the specification that are most critical for conformance.
Specific issues are presented by “external specifications” referenced by Java
specifications. See “External Specifications” below for a more detailed discussion
of this problem.
3. Tests. You develop test cases for the assertions to be tested. Test cases must be
identified and associated with the assertions they test.
4. Coverage is evaluated. Assertion coverage metrics are calculated. If Sun's Spec
Trac Tool is used for specification mark-up and test identification, and you first
bind assertions to test cases, these metrics can be calculated automatically.
External Specifications
You may wish to make a distinction between Java specifications and external
specifications. External specifications are typically from independent standards
bodies that are referenced by Java specifications. Often a relatively “thin” Java API
is provided, but reference is made to “dense” external specifications. For example,
the relatively small JAXP API references and in some sense includes the extremely
complex W3C XML language specifications.
Whether or not these external specifications should be marked up for assertion
classification with the same rigor as core Java specifications, and the thoroughness
with which the assertions derived from them should be tested, will depend on the
precise language used in the specification.
Specification leads should choose their language carefully, lest it inadvertently
impose significant TCK test development requirements.
Consider as an example a Java API to invoke a compiler for a complex language
that is defined in external specification. The Java API could be written in an
“exclusive” or an “inclusive” manner.
An inclusive specification might state:
When invoked via the ‘compile(file)’ method, the compiler reads
the file, which is assumed to contain a program in ’X’ language.
If the program is syntactically correct the method returns true
else it returns false.
This statement should probably be interpreted as two assertions (one for
syntactically correct, and one for incorrect program files). However, the appropriate
number of test cases for each assertion is likely to be many thousands for even a
Appendix C Measuring TCK Test Coverage 57
moderately complex language, since a full range of valid and invalid inputs should
be tested. The identification and construction of these test cases would require a
complete mark-up of the external specification.
Conversely, an exclusive specification might state:
When invoked via the compile(file) method, the compiler reads the
file, which is assumed to contain a program in ’X’ language. If
the compiler determines that the program is syntactically correct
the method returns true else it returns false. How the compiler
makes that determination, and whether or not it does so in
conformance with the specifications for the ’X’ language is
outside the bounds of this specification.
In this situation, a relatively small number of test cases should be adequate to
verify that the invoking method has been constructed properly, however, it would
not be necessary to exhaustively test the full range of valid and invalid program
file inputs.
It might be advisable under these circumstances to reference an external
conformance test suite that could be used to verify the correct behavior of the
compiler.
Assertion Coverage Metrics
The following metrics can be calculated for each package in the technology
implementation.
“Specification Testability” on page 57
“Assertion Coverage (Breadth)” on page 58
“Assertion Coverage (Depth)” on page 58
Note Any tests that are delivered with a TCK, but are excluded from test runs,
must also be excluded from coverage calculations.
Specification Testability
Specification testability measures how testable the specification is, and the extent to
which it encourages application portability.
If the specification is so ambiguous or incomplete that a significant proportion of
its assertions cannot be tested, even high assertion coverage of those assertions that
are testable cannot promote conformance among implementations.
Similarly, while it is possible to test implementations of specifications that contain
significant portions of optional functionality, real-world applications are unlikely to
be portable across such implementations due to the different sets of implemented
features.
58 TCK Project Planning and Development Guide August, 2003
Metrics
Total assertions = total number of identified assertions derived from the
specification.
Implementation-specific assertions = number of identified assertions that are
classified as implementation-specific.
Ambiguous assertions = number of identified assertions that are classified as
ambiguous.
Testable assertions = number of identified assertions that are classified as
testable.
Testability ratio = testable assertions/total assertions expressed as a percentage
Based on this formula, your TCK Project Plan might set a target testability ratio of
at least 70% averaged across all packages.
Assertion Coverage (Breadth)
Assertion coverage (breadth) measures how broadly the TCK tests the
implementation by calculating how many of the identified, testable assertions are
actually tested at least once, no matter how superficially.
Metric
Testable assertions = the number of identified, testable assertions derived from
a portion of the specification.
Tested assertions = the number of those assertions for which at least one test
case is provided.
Breadth ratio = tested assertions / testable assertions expressed as a percentage
Based on this formula, your TCK Project Plan might set a target of the following
minimums:
Averaged across all packages a breadth ratio of at least 75%.
For each package a minimum breadth ratio of at least 30%.
Assertion Coverage (Depth)
Assertion coverage (depth) measures the completeness with which the TCK tests
the implementation, by calculating the number of test cases actually provided as a
proportion of the total number of test cases that would be required to thoroughly
test the implementation.
For information on how to estimate the number of test cases required to thoroughly
test an implementation, see the discussions of Equivalence Class Partitioning and
Boundary Value Analysis in Java Technology Test Suite Development Guide.
Appendix C Measuring TCK Test Coverage 59
Metric
Testable assertions = the number of identified, testable assertions derived from
a portion of the specification.
Provided test cases = the total number of test cases provided to test those
assertions.
Required test cases = the total number of test cases that would be required to
thoroughly test those assertions.
Test cases per assertion = provided test cases / testable assertions.
Depth ratio = provided test cases / required test cases, expressed as a percentage
API Coverage
This section discusses API member coverage and the processes and metrics used to
measure it.
Process
API coverage, while not as useful as assertion coverage for determining TCK
completeness, provides information about the percentage of API members that are
directly referenced by the TCK. This measurement is determined by counting the
number of public API members (that is, public methods, constructors and fields)
directly referenced by the TCK tests and comparing them to the total number of
public API members defined by the specification.
API Coverage Metric
The API coverage metric measures how many API members are directly referenced
at least once by the TCK tests. Ideally, all API members should be accessed at least
once by the TCK tests meaning that all API members defined by the Specification
are tested at least marginally by the TCK.
Metric
Accessed API members = number of API members referenced by TCK tests.
Spec API members = number of API members defined by the Specification.
API coverage ratio = accessed API members/ Spec API members, expressed as a
percentage
60 TCK Project Planning and Development Guide August, 2003
Based on this formula, your TCK Project Plan might set a target for API coverage
ratio. A ratio of at least 90% is recommended.
Signature Coverage
The signature coverage metric ensures that all required elements in the
specification are present in the API and that no extra elements are present that
improperly extend the API.
The recommended target is 100% of signatures verified.
61
Java TCK and CTT Glossary
The definitions in this glossary are intended for Java™ Compatibility Test Tools
(Java CTT) and Java Technology Compatibility Kits (TCK). Some of these terms
may have different definitions or connotations in other contexts. This is a generic
glossary covering all of Sun’s CTTs and TCKs, and therefore it may contain some
terms that are not relevant to the specific product described in this manual.
active agent A type of test agent that initiates a connection to the JavaTest harness. Active
test agents allow you to run tests in parallel using many agents at once and to
specify the test machines at the time you run the tests. Use the agent monitor
to view the list of registered active agents and synchronize active agents with
the JavaTest harness before running tests. See also test agent, passive agent, and
JavaTest agent.
active applet
instance An applet instance that is selected on at least one of the logical channels.
agent monitor The JavaTest window that is used to synchronize active agents and to monitor
agent activity. The Agent Monitor window displays the agent pool and the
agents currently in use.
agents See test agent, active agent, passive agent, and JavaTest agent.
all values All of the configuration values required for a test suite. All values includes the
test environment values specific to that test suite and the JavaTest standard
values.
API member Fields, methods and constructors for all public classes that are defined in the
specification.
API member tests Tests (sometimes referred to as class and method tests) that are designed to
verify the semantics of API members.
appeals process A process for challenging the fairness, validity, accuracy, or relevance of one
or more TCK tests. Tests that are successfully challenged are either corrected
or added to the TCK’s Exclude List. See also first-level appeals process, second-
level appeals process, and Exclude List.
62 TCK Project Planning and Development Guide August, 2003
Application IDentifier
(AID) An identifier that is unique in the TCK namespace. As defined by
ISO 7816-5, it is a string used to uniquely identify card applications and
certain types of files in card file systems. An AID consists of two distinct
pieces: a 5-byte RID (resource identifier) and a 0 to 11-byte PIX (proprietary
identifier extension). The RID is a resource identifier assigned to companies
by ISO. The PIX identifiers are assigned by companies. There is a unique AID
for each package and a unique AID for each applet in the package. The
package AID and the default AID for each applet defined in the package are
specified in the CAP file. They are supplied to the converter when the CAP
file is generated.
Application
Programming
Interface (API) An API defines calling conventions by which an application program accesses
the operating system and other services.
Application Protocol
Data Unit (APDU) A script that gets sent to the test applet as defined by ISO 7816-4.
assertion A statement contained in a structured Java technology API specification to
specify some necessary aspect of the API. Assertions are statements of
required behavior, either positive or negative, that are made within the Java
technology specification.
assertion testing Conformance testing based on testing assertions in a specification.
atomic operation An operation that either completes in its entirety (if the operation succeeds)
or is not completed at all (if the operation fails).
automatic tests Test that run without any intervention by a user. Automatic tests can be
queued up and run by the test harness and their results recorded without
anyone being present.
behavior-based
testing A set of test development methodologies that are based on the description,
behavior, or requirements of the system under test, not the structure of that
system. This is commonly known as “black-box” testing.
boundary value
analysis A test development technique which entails developing additional tests based
on the boundaries defined by previously categorized equivalence classes.
class The prototype for an object in an object-oriented language. A class may also be
considered a set of objects which share a common structure and behavior. The
structure of a class is determined by the class variables which represent the
state of an object of that class and the behavior is given by a set of methods
associated with the class. See also classes.
classes Classes are related in a class hierarchy. One class may be a specialization (a
“subclass”) of another (one of its “superclasses”), may be composed of other
classes, or may use other classes in a client-server relationship. See also class.
Java TCK and CTT Glossary 63
configuration Information about your computing environment required to execute a
Technology Compatibility Kit (TCK) test suite. The JavaTest harness version 3.x
uses a configuration interview to collect and store configuration information.
The JavaTest harness version 2.x uses environment files and parameter files to
obtain configuration data.
configuration editor The dialog box used by JavaTest harness version 3.x to present the configuration
interview.
configuration
interview A series of questions displayed by the JavaTest harness version 3.x to gather
information from the user about the computing environment in which the
TCK is being run. This information is used to produce a test environment that
the JavaTest harness uses to execute tests.
configuration value Information about your computing environment required to execute a TCK
test or tests. The JavaTest harness version 3.x uses a configuration interview to
collect configuration values. The JavaTest harness version 2.x uses
environment files and parameter files to obtain configuration data.
conformance rules Define the criteria a Java technology implementation must meet in order to be
certified as “conformant” with the technology specification. See also
conformance testing.
conformance testing The process of testing an implementation to make sure it is conformant with
the corresponding Java technology specification. A suite of tests contained in
a Technology Compatibility Kit (TCK) is typically used to test that the
implementation meets and passes all of the conformance rules of that
specification.
environment files Files used by the JavaTest harness 2.x to configure how the JavaTest harness
runs the tests on your system. Environment files have the filename extension
of .jte. Environment files are used in conjunction with parameter files.
equivalence class
partitioning A test development technique which entails breaking a large number of tests
into smaller subsets with each subset representing an equivalent category of
test.
Exclude List A list of TCK tests that a technology implementation is not required to pass in
order to certify conformance. The JavaTest harness uses exclude list files
(*.jtx), to filter out of a test run those tests that do not have to be passed.
The exclude list provides a level playing field for all implementors by
ensuring that when a test is determined to be invalid, no implementation is
required to pass it. Exclude lists are maintained by the Maintenance Lead (ML)
and are made available to all technology licensees. The ML may add tests to
the exclude list for the test suite as needed at any time. An updated exclude
list replaces any previous exclude lists for that test suite.
first-level appeals
process The process by which a technology implementor can appeal or challenge a
TCK test. First-level appeals are resolved by the Expert Group responsible for
the technology specification and TCK. See also appeals process and second-level
appeals process.
64 TCK Project Planning and Development Guide August, 2003
framework See test framework.
Graphical User
Interface (GUI) Provides application control through the use of graphic images.
HTML test
description A test description that is embodied in an HTML table in a file separate from
the test source file.
implementation See technology implementation.
instantiation In object-oriented programming, means to produce a particular object from its
class template. This involves allocation of a data structure with the types
specified by the template, and initialization of instance variables with either
default values or those provided by the class’s constructor function.
interactive tests Tests that require some intervention by the user. For example, the user might
have to provide some data, perform some operation, or judge whether or not
the implementation passed or failed the test.
Java™ 2, Standard
Edition (J2SE™)
platform A set of specifications that defines the desktop runtime environment required
for the deployment of Java applications. The J2SE implementations are
available for a variety of platforms, but most notably the Sun Solaris
operating environment and Microsoft Windows.
Java Application
Manager (JAM) A native application used to download, store and execute Java applications.
Java Archive (JAR) A platform-independent file format that combines many files into one.
Java Compatibility
Test Tools (Java
CTT) Tools, documents, templates, and samples that can be used to design and
build TCKs. Using the Java CTT simplifies conformance test development
and makes developing and running tests more efficient.
Java Community
Process (JCP) An open organization of international Java developers and licensees whose
charter is to develop and revise Java technology specifications, and their
associated Reference Implementation (RI), and Technology Compatibility Kit
(TCK).
Java Platform
Libraries The class libraries that are defined for each particular version of a Java
technology in its Java technology specification.
Java Specification
Request (JSR) The actual descriptions of proposed and final technology specifications for
the Java technology.
Java technology A Java technology is defined as a Java technology specification and its Reference
Implementation (RI). Examples of Java technologies are Java 2 Platform,
Standard Edition (J2SE™), the Connected Limited Device Configuration
(CLDC), and the Mobile Information Device Profile (MIDP).
Java TCK and CTT Glossary 65
Java Technology
Compatibility Kit See Technology Compatibility Kit (TCK).
Java technology
specification A written specification for some aspect of the Java technology.
JavaTest agent A test agent supplied with the JavaTest harness to run TCK tests on a Java
implementation where it is not possible or desirable to run the main JavaTest
harness. See also test agent, active agent, and passive agent.
JavaTest harness A test harness that has been developed by Sun to manage test execution and
result reporting for a Technology Compatibility Kit (TCK). The harness
configures, sequences, and runs test suites. The JavaTest harness is designed
to provide flexible and customizable test execution. It includes everything a
test architect needs to design and implement tests for Java technology
specifications.
keywords Used to direct the JavaTest harness to include or exclude tests from a test run.
Keywords are defined for a test by the test suite architect.
Maintenance Lead
(ML) The person responsible for maintaining an existing Java technology specification
and related Reference Implementation (RI) and Technology Compatibility Kit
(TCK). The ML manages the TCK appeals process, Exclude List, and any
revisions needed to the specification, TCK, or RI.
methods Procedures or routines associated with one or more classes,inobject-oriented
languages.
MultiTest A JavaTest library class that enables tests to include multiple test cases. Each
test case can be addressed individually in a test suite Exclude List.
namespace A set of names in which all names are unique.
object-oriented A category of programming languages and techniques based on the concept
of objects which are data structures encapsulated with a set of routines, called
methods, which operate on the data.
objects In object-oriented programming, objects are unique instances of a data
structure defined according to the template provided by its class. Each object
has its own values for the variables belonging to its class and can respond to
the messages (methods) defined by its class.
packages A namespace within the Java programming language. It can have classes and
interfaces. A package is the smallest unit within the Java programming
language.
parameter files Files used by the JavaTest harness to configure individual test runs. For
JavaTest harness version 2.x parameter files have the filename extension
*.jtp. For JavaTest harness version 3.x parameter files have the filename
extension *.jti.
passive agent A type of test agent that must wait for a request from the JavaTest harness
before they can run tests. The JavaTest harness initiates connections to
passive agents as needed. See also test agent, active agent, and JavaTest agent.
66 TCK Project Planning and Development Guide August, 2003
prior status A JavaTest filter used to restrict the set of tests in a test run based on the last
test result information stored in the test result files (.jtr).
Profile Specification A specification that references one of the Platform Edition Specifications and
zero or more other Java technology specifications (that are not already a part
of a Platform Edition Specification). APIs from the referenced Platform
Edition must be included according to the referencing rules set out in that
Platform Edition Specification. Other referenced specifications must be
referenced in their entirety.
Program Management
Office (PMO) The administrative structure that implements the Java Community Process
(JCP).
Reference
Implementation (RI) The prototype or proof of concept implementation of a Java technology
specification. All new or revised specifications must include an RI. A
specification RI must pass all of the TCK tests for that specification.
second-level appeals
process Allows technology implementors who are not satisfied with a first-level
appeal decision to appeal the decision. See also appeals process and first-level
appeals process.
signature file A text representation of the set of public features provided by an API that is
part of a finished TCK. It is used as a signature reference during the TCK
signature test for comparison to the technology implementation under test.
signature test Checks that all the necessary API members are present and that there are no
extra members which illegally extend the API. It compares the API being
tested with a reference API and confirms if the API being tested and the
reference API are mutually binary compatible.
specification See Java technology specification.
standard values A configuration value used by the JavaTest harness to determine which tests in
the test suite to run and how to run them. The user can change standard
values using either the all values or Standard Values view in the configuration
editor.
structure-based
testing A set of test development methodologies that are based on the internal
structure or logic of the system under test, not the description, behavior, or
requirements of that system. This is commonly known as “white-box” or
“glass-box” testing. Conformance testing does not make use of structure-
based test techniques.
system
configuration Refers to the combination of operating system platform, Java programming
language, and JavaTest harness tools and settings.
tag test description A test description that is embedded in the Java language source file of each
test.
Java TCK and CTT Glossary 67
TCK coverage file Used by the Java CTT Spec Trac tool to track the test coverage of a test suite
during test development.
Technology
Compatibility Kit
(TCK) The suite of tests, tools, and documentation that allows an implementor of a
Java technology specification to determine if the implementation is compliant
with the specification.
technology
implementation Any binary representation of the form and function defined by a Java
technology specification.
technology
specification See Java technology specification.
test agent A Java application that receives tests from the test harness, runs them on the
implementation being tested, and reports the results back to the test harness.
Test agents are normally only used when the TCK and implementation being
tested are running on different platforms. See also active agent, passive agent,
and JavaTest agent.
test The source code and any accompanying information that exercise a particular
feature, or part of a feature, of a technology implementation to make sure that
the feature complies with the Java technology specification’s compatibility rules.
A single test may contain multiple test cases. Accompanying information may
include test documentation, auxiliary data files, or other resources used by
the source code. Tests correspond to assertions of the specification.
test cases A small test that is run as part of a set of similar tests. Test cases are
implemented using the JavaTest MultiTest library class. A test case tests a
specification assertion, or a particular feature, or part of a feature, of an
assertion.
test command A class that knows how to execute test classes in different environments. Test
commands are used by the test script to execute tests.
test command
template A generalized specification of a test command in a test environment. The test
command is specified in the test environment using variables so that it can
execute any test in the test suite regardless of its arguments.
test description Machine readable information that describes a test to the test harness so that it
can correctly process and run the related test. The actual form and type of test
description depends on the attributes of the test suite. A test description exists
for every test in the test suite and is read by the test finder. When using the
JavaTest harness, the test description is a set of test-suite-specific name/value
pairs in either HTML tables or Javadoc-style tags.
test environment Consists of one or more test command template that the test script uses to
execute tests and set of name/value pairs that define test description entries or
other values required to run the tests.
test execution model The steps involved in executing the tests in a test suite. The test execution
model is implemented by the test script.
68 TCK Project Planning and Development Guide August, 2003
test finder When using the JavaTest harness, a nominated class, or set of classes, that read,
verify, and process the files that contain test description in a test suite. All test
descriptions that are located or found are handed off to the JavaTest harness
for further processing.
test framework Software designed and implemented to customize a test harness for a
particular test environment. In addition to the test harness, a test framework
might (or might not) include items such as a: configuration interview, Java
Application Manager (JAM), test agent, test finder, test script, and so forth. A test
framework might also include user-supplied software components (plug-ins)
to provide support for implementation-specific protocols.
test harness The applications and tools that are used for test execution and test suite
management. The JavaTest harness is an example of a test harness.
test script A Java class whose job it is to interpret the test description values, run the
tests, and then report the results back to the JavaTest harness. The test script
must understand how to interpret the test description information returned
to it by the test finder.
test specification A human-readable description, in logical terms, of what a test does and the
expected results. Test descriptions are written for test users who need to
know in specific detail what a test does. The common practice is to write the
test specification in HTML format and store it in the test suite’s test directory
tree.
test suite A collection of tests, used in conjunction with the test harness to verify
conformance of the licensee’s implementation to a Java technology specification.
Every Technology Compatibility Kit (TCK) contains one or more test suites.
work directory A directory associated with a specific test suite and used by the JavaTest
harness to store files containing information about the test suite and its tests.
69
Index
Symbols
.jte files, 63
.jtp files, 65
.jtx files, 63
A
active agent, 61
active applet instance, 61
Agent Monitor, 61
agent see test agent
AID see Application IDentifier
all values, 61
APDU see Application Protocol Data Unit
API, 62
API Coverage Tool, 10
coverage ratio, 59
coverage report, 31
coverage targets, 31
reports, 30
API member, 61
appeals process, 17, 43, 47, 61
appeal form, 45
criteria, 45
first level, 43, 63
forms for, 45
guidelines for, 44
overview of, 43
requirements of, 44
response form, 45
second level, 43, 66
Application IDentifier, 62
Application Protocol Data Unit, 62
assertion testing (definition of), 62
assertions, 15, 62
atomic operation, 62
audit process, 23
automatic tests, 62
B
behavior-based testing, 62
black-box testing, 62
boundary value analysis, 54, 62
C
class and method tests, 34
classes, 62
code conventions, 16
compatibility testing see conformance testing
configuration, 63
Configuration Editor, 63
conformance rules, 14, 63
conformance testing, 63
importance of, 2
vs product testing, 5
CTT see Java Compatibility Test Tools
D
descriptions, test, 67
documentation, 22
documentation plan, 50
E
environment files, 63
equivalence class partitioning, 54, 63
70 TCK Project Planning and Development Guide August, 2003
Exclude Lists, 17, 18, 63
external specifications, 56
F
first-level appeals process, 63
functional, 34
functional tests, 34
G
glass-box testing, 66
Graphical User Interface, 64
GUI see Graphical User Interface
H
HTML test description, 64
I
IEEE standard 829-1983, 51
implementation see technology implementation
Instantiation, 64
interactive tests, 64
ISO 7816-4, 62
J
J2SE see Java 2 Standard Edition
JAM see Java Application Manager
JAR see Java Archive
Java 2 Standard Edition, 64
Java API Coverage Tool see API Coverage Tool
Java Application Manager, 64
Java Archive, 64
Java Community Process, 4, 64
stages of, 8
Java Compatibility Test Tools, 9, 64
API Coverage Tool, 10
documentation set, 26
downloading, 26
JavaTest harness, 9
licenses, 26
Sample TCK, 10
Signature Test Tool, 9
Spec Trac Tool, 9
TCK Project Plan Template, 10
TCK User’s Guide Template, 10
Test Suite Development Guide,10
time estimates based on, 39
training in, 28
where to find, vii
Java Platform Libraries, 64
Java TCK User’s Guide Template, 10
Java technology, 64
Java Technology Compatibility Kit see Technology
Compatibility Kit, 65
Java technology specification, 65
components of, 4
coverage metrics, 57
interactive development of, 5
markup of, 27
Java technology specifications
external specifications vs, 56
Javadoc, 9
JavaTest Agent, 21
JavaTest Architects Guide, 9
JavaTest harness, 9, 20
configuration editor, 21
configuration interview, 21
JCP see Java Community Process
jte files, 63
jtp files, 65
jtx files, 63
K
keywords, 65
M
Maintenance Lead, 38, 65
method, 65
ML see Maintenance Lead
MultiTest, 65
N
namespace, 65
O
object-oriented, 65
objects, 65
P
package, 65
parameter files, 65
planning a TCK, 33
Index 71
API implementation, 48
API tests, 49
application manager, 49
decisions, initial, 36
design plan, 48
development stages, 8
documentation plan, 50
hardware issues, 48
IEEE standard 829-1983, 51
integration plan, 13
key decisions, 3
overall plan, 13, 47
personnel, 38
planning documents, 13
project plan, 13
QA plan, 51
questions to ask, 36
summary overview of, 37
TCK Project Plan Template, 37
test agent, 37
test cast specifications, 49
test coverage, 36
test harness, 36
test plan, 13
time estimates see time estimates
timeline, 8
types of tests, 49
PMO see Program Management Office, 66
prior status, 66
Profile Specification, 66
Program Management Office, 66
Program Manager, 38
Q
QA plan, 51
quality assurance engineer, 38
R
Reference Implementation, 66
RI see Reference Implementation, 66
S
Sample TCK, 10
second-level appeal process, 66
signature file, 66
signature tests, 66
source code, 22
Spec Trac Tool, 9
coverage targets, 31
Specification Lead, 38
specification see Java technology specification
specifications, external, 56
structure-based testing, 66
system configuration, 66
T
tag test description, 66
TCK Project Plan Template, viii, 10, 33, 37
TCK see Technology Compatibility Kit, 67
technical writer, 39
Technology Compatibility Kit, 2, 67
appeals process see appeals process
audit process, 23
components of, 13
conformance rules see conformance rules
decisions, initial, 36
delivery of, 48
development timeline, 8
documentation of, 22
Java Community Process and, 8
JavaTest harness, 20
key decision points, 3
planning of see planning a TCK
product, 6
questions to ask, 36
requirements of, 6
scope of task, 1
target coverage, 47
test harness, 18
test specifications, 13
time estimates see time estimates
users guide, 22
vs internal testing, 6
technology implementation, 67
technology see Java technology
test agent, 20, 67
test architect, 38
test case specifications, 22
test cases, 67
test command templates, 67
test commands, 67
test descriptions, 22, 67
test developer, 38
test execution mode, 67
test finder, 68
test framework, 68
72 TCK Project Planning and Development Guide August, 2003
test harness, 18
test script, 68
test specification, 68
Test Suite Development Guide, 10
test suites, 15, 68
tests, 15, 67
assertions, 15
audit process, 23
automatic, 62
class and method, 34
code conventions, 16
guidelines, 15
harness & technology different machines, 21
interactive, 64
requirements of, 15
specifications, 49
types of, 49
time estimates
application manager, 41
assertions, number of, 40
build environment, 41
coverage breadth, 40
development rate, 40
documentation, 41
framework development time, 41
miscellaneous requirements, 41
number of tests, 40
QA time, 41
specification changes, 41
test agent, 41
test suite development time, 40
tests per engineer, 40
tests, number of, 40
training time, 41
TSDG see Test Suite Development Guide
W
white-box testing, 66
work directory, 68