Pre-Construction Meeting Agenda
Project Numbers and Name
Page 3 of 5
i. First ???day of every month at ??:?? a.m. or p.m.
ii. Contractor will conduct meeting and distribute meeting minutes
iii. Must review: Last 30 days of progress, Upcoming 30 days of work, Weather &
Labor Report, Schedule & Status Report, Action Item List, RFI Log, Submittal Log,
Change Order Log, and Project Issues.
iv. This meeting is for Owner/User updates and coordination with the Owner/User.
This meeting is NOT for the Contractor to coordinate with the Subcontractors.
f. Door Hardware and Keying Meeting
18. Change Orders
a. Change Orders - Documentation - no prior work, unless authorized in writing
b. For ALL IHL projects, the Change Order must be transmitted to Facilities Planning. Facilities Planning
will then send an approval request to IHL. The Change Order cannot be executed by the University
until IHL approves the Change Order.
c. Change Orders must be provided with detailed cost breakdowns and the written directions or
drawings from the Architect that the Contractor used for pricing.
d. Contractor must follow mark-up requirements as identified in the Supplementary Conditions.
19. Pay Applications
a. Minimum two (2) original copies.
b. Method of approving monthly payment requests
c. Application for Payment must be submitted at the beginning of every month. The application shall
be for the prior month in its entirety.
d. AIA Form G702 with FormG703
e. Contractor’s letter of statement regarding project schedule, weather days with NOAA backup, and,
if necessary, a plan of action to resolve schedule issues
f. All applications for payment after the first application must include the Affidavit Certifying Payment
to All Subcontractors.
g. The first application for payment will not be considered without a complete approved schedule of
values, construction schedule, project contact list, and submittal schedule.
20. Sub-Contractor Coordination
a. Contractor's duty to coordinate work of separate contractors
b. Surveyor to check foundation wall if location critical
c. Ready mix plant, file delivery tickets, slump tests, cylinders
d. What is expected of masonry work, mortar additive Problems with hollow metal (install proper fire
labels) Problems with fire damper installation
21. Utility and Outage Issues
a. Coordinate any utilities supplied by Owner
b. Coordinate outages and work in existing building with Owner
22. As-Built Documents
a. Contractor must maintain, at all times, As-Built Documents.
b. Design Professional will review the maintenance of the As-Built Documents at each site visit.
c. Accurate As-Built Documents are required as part of Project Close Out Documents.
PROJECT SITE
23. Supplementary Conditions – Pay close attention to Supplementary Conditions.
24. Work Hours and Non-Interference of University Operations
a. See Supplementary Conditions